| Title | S45C changes to proposal | Ministerial Statement | Last updated |
|---|---|---|---|
| Kwinana Gas-Fired Power Station (Water Cooled Condenser) |
Attachment to Statement 698 - Amendment of Schedule 1 – Key Proposal Characteristics Table 1 - change to proposal approved on 15 August 2007. Attachment 2 to Statement 698
Changes approved under S45c on 3 November 2020. Attachment 3 to Statement 698 - Increase in power generation capacity and thermal efficiency. Changes approved under S45c on 22 April 2024. |
|
April 24, 2024 |
| Yanchep Rail Extension: Part 1 – Butler to Eglinton |
Attachment 1 to Statement 1100 - Change to the authorised extent in Schedule 1 Table 2 in Ministerial Statement 1100, including: Change approved under S45c on 12 October 2020. Attachment 2 to Statement 1100 - Increase the development envelope from 57.18 hectares (ha) to 60.69 ha. Decrease the authorised extent of native vegetation clearing from 32.3 ha to 31.64 ha. Decrease the authorised extent of Carnaby’s cockatoo habitat that can be cleared from 44.7 ha to 43.98 ha. Update Figures 1 to 4 to reflect the amendments to the development envelope. Updated coordinates defining the Yanchep Rail Extension Part 1 – Butler to Eglinton development envelope.Change approved under S45c on 19 April 2024. |
|
April 19, 2024 |
| St Ives Gold Mine – Beyond 2018 Project (Revised Proposal) |
Attachment 1 to Statement 1128 - Increase in the size of the development envelope by 572 hectares. Inclusion of a hybrid energy-source powered microgrid (hybrid microgrid) within the land-based operations. Change to conditions approved 18 December 2023. Attachment 2 to Statement 1128 - Increase to extent of development envelope by 4 ha. Realignment of a transmission line associated with the hybrid energy-source powered microgrid.. Change to conditions approved 19 April 2024. |
|
April 19, 2024 |
| Asian Renewable Energy Hub |
Attachment 1 to Statement 1153 - Change to condition 6, condition 7 and condition 8 and Table 3 of Schedule 1. Changes approved under s.45C on 11 April 2024 |
|
April 11, 2024 |
| Rockingham Industrial Zone Strategic Environmental Assessment (Formerly IP14) |
Attachment 1 to Statement 863 – Add 4.36 hectares to the Rockingham Industrial Zone Strategic Proposal area – change to proposal approved under section 45C on 4 October 2013. Attachment 2 to Statement 863 – Addition of 197.54 hectares (ha) to the original proposal area and inclusion of the Conservation Area of 91 ha in Table 2 – change to proposal approved under section 45C on 22 October 2014. Attachment 3 to Statement 863 – Change the Conservation Area boundaries to remove a rail corridor from the south and provide additional land in the north – change to proposal approved under section 45C on 11 November 2015. |
|
April 3, 2024 |
| Mt Weld Rare Earths Project – Life of Mine Proposal |
Attachment 1 to Statement 1216 - Increase in maximum extent of tailings dam area from 170 hectares to 280 hectares. Change to conditions approved under s.45C on 26 March 2024. |
|
March 26, 2024 |
| Koodaideri Iron Ore Mine and Infrastructure Project |
Attachment 1 to Statement 999 - Changes:
Change to conditions approved under S45C on 6 September 2017. Attachment 2 to Statement 999 - Amendment to condition 14-2, approved under S46C on 4 January 2021. Attachment 3 to Statement 999 - Changes: |
|
March 7, 2024 |
| Ammonium Nitrate Production Expansion Project: Phase 2, Kwinana |
Attachment 1 to Statement 875 – Removal of "Greenhouse gas emissions" – change to proposal approved under section 45C on 3 January 2013. Attachment 2 to Statement 875 – Increase the boundary of Project Area; addition of an ammonium nitrate emulsion plant and associated infrastructure; remove elements that are not a significant key characteristic relevant to the environment or are regulated under Part V of the Environmental Protection Act 1986; and update Figures and reference coordinates - change to proposal approved under section 45C on 24 January 2017. Attachment 3 to Statement 875 – Removal of the authorised extent of up to 2.5 ML/day of liquid waste output from the Key Characteristics Table - change to proposal approved under section 45C on 13 August 2018. Attachment 4 to Statement 875 – Debottlenecking at three existing nitric acid and ammonium nitrate (NAAN) Change to proposal approved under section 45C on 7 March 2024. |
|
March 7, 2024 |
| Woodside Solar Facility |
Attachment 1 to Ministerial Statement 1212 - An increase in the total development envelope by 0.96 ha (from 1,100.3 ha to 1,101.26 ha) for the construction of an access road connecting the Woodside Solar Facility to the North West Coastal Highway. The Proposal Content Document published in the Statement of Reasons for the section 45c supersedes the ‘Proposal Content Document attachment 2’ referred to in Ministerial Statement 1212. Changes approved under s. 45C on 29 February 2024. |
|
February 29, 2024 |
| Coyote Gold Mine – Stage 2 (Sandpiper and Kookaburra Open Pits and Haul Road) 280km South-East of Halls Creek |
Attachment 1 to Statement 749 – Increase to mine life, ore mined and waste rock volumes, deepening of the Kookaburra pit, and an increase to pit and land disturbance areas – change to proposal approved under s45C on 28 September 2011. Attachment 2 to Statement 749 – Development of Osprey Satellite Pit – change to proposal approved under section 45C on 1 November 2012. Attachment 3 to Statement 0749 - Increase the clearing of native vegetation from 120 hectares to 152.95 hectares. Increase the size of Kookaburra pit from 7.3 hectares to 7.8 hectares. Increase the life of project from 25 months to 31 months. Change to proposal approved under section 45C on 23 February 2024 |
|
February 23, 2024 |