S45C changes to proposal

Title S45C changes to proposal Ministerial Statement Last updated
Gorgon Gas Development Revised and Expanded Proposal: Barrow Island Nature Reserve

Attachment 1 to Statement 800 - Change to clarify that discharge of waste from marine vessels will be in accordance with MARPOL 73/78. Change to proposal approved under s45C on 23 February 2010.

Attachment 2 to Statement 800 - Change to development and usage of boil off gas flares and increase of seawater volume intake during the construction period. Change to proposal approved under s45C on 26 February 2010.

Attachment 3 to Statement 800 - Use of seawater for construction earthworks on the LNG treatment plant site. Change to proposal approved under s45C on 23 March 2010.

Attachment 4 to Statement 800 - Increase in construction duration and construction workforce – change to proposal approved under s45C on 29 April 2011.

Attachment 5 to Statement 800 – To modify the carbon dioxide (CO2) pipeline from an above ground installation to a buried installation - change to proposal approved under s45C on 2 June 2011.

Attachment 8 to Statement 800 - Deletion of construction duration and construction workforce detailed in Attachment 4 and correction of clerical error in Attachment 5 – change to proposal approved under section 45C on 26 June 2013.

Attachment 9 to Statement 800 - The temporary venting or flaring of gas liberated during the monoethylene glycol (MEG) regeneration process (MEG flash vapours) until the completion of commissioning of piping to route the MEG flash vapour to the condensate stabilisation overhead unit or until 31 December 2021 (whichever is earlier), and after that time when normal operations are not available (i.e. during periods of process shut-down and start-up, and upset conditions) – change to proposal approved under section 45C on 3 April 2020.

Attachment 10 to Statement 800 - Amendment of descriptions of Feed Gas Pipeline System and shore crossing to incorporate additional power/control infrastructure; Describe shore crossing point of domestic gas pipeline; Amendments to Schedule 3, removing items 6 (Carbon Dioxide Injection System) and 10 (Greenhouse Gas Abatement) as they are no longer relevant. Changes approved under s.45C on 24 October 2022.

Attachment 11 - An additional pressure management drill centre (DC-F) and additional wells for pressure management, pressure management water injection, anode and reservoir surveillance at existing drill centres (DC-A and DC-C). Changes approved under s.45C on 28 September 2024.

Ministerial Statement 800.pdf (PDF, 837.68 KB) September 28, 2024
Utah Point Berth Project (Stage B)

Attachment 1 to Statement 788 - Removal of the references to Dust and Noise Suppression, and Stormwater Management from the Key Characteristics Table - change approved under s45C on 14 December 2015.

Ministerial Statement 788 (PDF, 2.07 MB) September 27, 2024
State Barrier Fence Esperance Extension

Attachment 1 to Statement 1095 - Change to the authorised extent of the development envelope within which clearing and disturbance can occur. Change to the authorised extent of existing firebreaks and previously uncleared areas within which ongoing chaining can occur. Change to conditions related to terrestrial fauna (western ground parrot (Pezoporus flaviventris)). Changes approved under s. 45C on 18  September 2024

Ministerial Statement 1095.pdf (PDF, 1.69 MB) September 18, 2024
Turkey Point Access Road and Bridge

Attachment 1 to Statement 1192 - Amendments to introduction, condition 1, figure and schedule 1. Change to statement approved under s. 45C on 5 September 2024.

Statement 1192.pdf (PDF, 749.49 KB) September 5, 2024
Sodium Cyanide Plants (Liquid and Solid) at Kwinana and Transport of Sodium Cyanide by Road and Rail from Kwinana

Attachment 1 to Ministerial Statement 1196 - Amendment to the introduction, figures, schedule 1 and condition 1-1. Changes aproved under s. 45C on 27 August 2024.

Statement 1196.pdf (PDF, 1.77 MB) August 27, 2024
Browns Range Rare Earth Project

Attachment 1 to Ministerial Statement 986 - Revise the development envelope boundaries; and update Figures and reference to coordinates - change to proposal approved under section 45C on 12 April 2017.

Attachment 2 to Ministerial Statement 986 - Installation and operation of an Ore Sorting Circuit, resulting in higher radionuclide concentrations in sorted ore, intermediate process streams and the long-term storage of low-level radioactive waste (tailings). Change to proposal approved under section 45C on 4 September 2020.

Attachment 3 to Ministerial Statement 986 - Increase the disturbance footprint from 711 ha to 771 ha (8.4% increase) and an increase in the development envelope from 2,590 ha to 4,384 ha. Realignment of the development envelope and expansion of the borefield. Change to proposal approved under section 45C on 26 August 2024.

Ministerial Statement 986.pdf (PDF, 2.73 MB) August 26, 2024
Tropicana Gold Project

Attachment 1 to Statement 839 – implement a single cell tailings storage facility – change to proposal approved under section 45C on 19 November 2012.

Attachment 2 to Statement 839 – remove reference to ‘Mining rate’; ‘Stripping ratio’, ‘Communications’, and ‘Main power supply’; increase water supply from ‘Up to 7 gl/year’ to ‘Up to 9 Gl per year’; increase the ‘Disturbance Area’ for the water supply area from 200 to 300 hectares; and update the figures and provide a table of coordinates defining disturbance envelopes – change to proposal approved under section 45C on 17 December 2014.

Attachment 3 to Statement 839 – increase height of waste landforms from 375 mRL to 417 mRL including the rehabilitation cover; remove the TSF specifications including the tailings deposition rate, number of TSF cells, disturbance footprint of the TSF and the maximum height of the TSF; and clarify that the overburden and waste is for the disposal in the waste landforms – change to proposal approved under section 45C on 8 December 2016.

Attachment 4 to Statement 839 – Changes:

  • change in the Short Description to include underground mining methods (Table 1); and
  • correct an administrative error for the authorised extent of the Infrastructure Development Envelope from 4269 ha to 18,494 ha (Table 2, Figure 1 and Table 4).

Changes to proposal approved under section 45C on 18 April 2019.

Attachment 5 to Statement 839 – Addition of the reference to the Kamikaze borefield in the key characteristics table. – change to proposal approved under section 45C on 13 October 2020.

Attachment 6 to Statement 839 – Changes:
• Amendment to Proposal: Increase the authorised extent of the open pit voids from 400 ha to 420 ha.
• Amendment to Proposal: Remove the maximum number, length and width of pits as physical elements of the proposal.
• No amendments to implementation conditions. – change to proposal approved under section 45C on 3 June 2022.

Attachment 7 to Statement 839 – Changes:
An increase in disturbance footprint within the Operational Development Envelope, for the construction and operation of infrastructure for the Renewable Energy Project comprising wind turbines, a solar farm and Battery Energy Storage System. No amendments to implementation conditions. Change to proposal approved under section 45C on 1 September 2023.

Attachment 8 to Statement 839 – Changes:
Single cell tailings storage facility with in-pit deposition. Change to proposal approved under section s45C on 22 March 2024.

Attachment 9 to Statement 839 – Condition 11 is deleted and replaced. Change to proposal approved under section s45C on 23 August 2024.

Ministerial Statement 839.pdf (PDF, 3.5 MB) August 23, 2024
Lumsden Point General Cargo Facility

Attachment 1 to Statement 967 - Include a 139.46 hectare development envelope for the temporary pipeline corridor; include DMMA B as a location for dewatering discharge; and update Figure 1 and delineation coordinates - change to proposal under s45C approved on 21 July 2017.

Attachment 2 to Statement 967 - Changes:

  • increase the dredging area development envelope by 6.9 ha to allow for deepening of the Stingray Creek Southern Swing Basin;
  • dredging volume increase by 400,000 m3 (total volume of 2.4 million m3); and
  • update Figure 1 and delineation coordinates.

Change to proposal under s45C approved on 14 April 2020.

Attachment 3 to Statement 967 -Changes:
• Include an increase to the causeway construction Development Envelope by 0.069 ha to allow for a straight path between DMMA C and the Land Backed Warf Area (total Development Area increase from 195.00 ha to 195.07 ha).
• Include an increase to average vertical dredge profile from 0.2 m to 0.5 m for berth pockets, shipping channel and turning basin dredging.
• Include onshore placement of remaining dredge material within Dredge Material Management Area C (DMMA C).- change to proposal under s45C approved on 27 September 2023.

Ministerial Statement 967.pdf (PDF, 1.48 MB) August 12, 2024
Revised Proposal for the Roy Hill Iron Ore Mine

Attachment 1 to Ministerial Statement 1189 - Condition 12-3 is deleted, and replaced. Change approved under S45C on 24 November 2022.

Attachment 2 to Ministerial Statement 1189 - Remove the total dissolved solid (TDS) limit of 50,000 mg/L for aquifer reinjection of excess mine dewater. Remove the TDS limit of 50,000 mg/L for dust suppression using excess mine dewater. Replace the introduction to reference a Proposal Content Document for the purposing of describing the approved proposal. Replace condition 1-1 to reflect the removal of the TDS limits. Change approved under S45C on 2 July 2024.

Statement 1189.pdf (PDF, 4.49 MB) July 2, 2024
Western Extension to the Dardanup Mineral Sands Project to include the Burekup Mineral Sands Deposit

Attachment 1 to Statement 789 - Change to the Burekup West mine disturbance footprint area - section 45C change to proposal approved on 7 July 2010.

Attachment 2 to Statement 789 - Change to the Burekup West Mine disturbance footprint area – change to proposal approved under s45C on 8 July 2011.

Ministerial Statement 789 - Western Extension to the Dardanup Mineral Sand s Project (Burekup Mineral Sand Project) (PDF, 2.12 MB) June 28, 2024

Pages