Attachment to Statement 633 – Redesign of the seawater intake facility – change to proposal approved under section 45C on 3 December 2004.
Attachment 1 to Statement 633 – Increase the maximum allowable area of the evaporation pond from 250 hectares to 391 hectares – change to proposal approved under section 45C on 22 December 2008.
Attachment 2 to Statement 633 – Construct and operate a Sands Reject Storage Facility - change to proposal approved under section 45C on 23 September 2010.
Attachment 3 to Statement 633 – Increase in disturbance footprint of 282 ha and removal of elements considered not environmentally relevant or managed under other legislation – change to proposal approved under section 45C on 12 August 2014.
Attachment 4 to Statement 633 - Changes:
- Administrative changes to better define the proposal in schedule 1
- Define development envelopes and combining project elements to allow flexibility in implementation, without increasing the authorised extent
- Include the access corridor (from Shoemaker-Levy to the process plant) to the authorised extent table
- Include the seawater pipeline and intake to the authorised extent table
- Add 289 hectares of cleared farmland for topsoil stockpiles, access tracks and miscellaneous infrastructure to the authorised extent table
- Amend the boundaries of the Halleys pit, Halleys overburden storage area and Hale- Bopp pit to incorporate historical clearing of native vegetation, without increasing the total authorised clearing extent
- Include the limestone quarry to Figure 1.
- Minor variation to the alignment of the access corridor in Figure 2
- Consistent naming of project elements between the tables and figures
- Remove elements that are duplicated.
Change to proposal approved under section 45C on 23 May 2019.
Attachment 5 to Statement 633 – Expansion of Southern Mines and Processing Development Envelope by 0.06 ha. Expansion of Tamarine Limestone Quarry Development Envelope by 71.8 ha and disturbance by 76.7 ha. Increase Seawater Pipeline and Intake Development Envelope by 20.3 ha. Increase Access Corridor Development Envelope by 1.6 ha - change to proposal approved under section 45C on 4 March 2025.