Attachment 1 to Statement 1164 - Changes:
- Increasing the development envelope from 354 hectares (ha) to 409.25 ha.
- Increasing the disturbance footprint from 345 ha to 397.75 ha within the development envelope.
Changes to proposal approved under S45c on 4 October 2021.
Attachment 2 to Statement 1164 - Changing production facility capacity from 250 terajoules per day to an annual limit of 91.25 petajoules. Increasing the size of the development envelope from 409.25 ha to 580.9 ha. Increasing the number of wells from 8 to 19. Increasing the disturbance footprint from 397.75 ha to 479.2 ha. Change to proposal approved under S45c on 16 April 2024.
Attachment 4 to Statement 1164 - Increasing the size of the development envelope from 580.9 ha to 581.2 ha. Increasing the disturbance footprint from 479.2 ha to 479.6 ha within the
development envelope. Increasing the gas production facility capacity from 91.25 Petajoules per annum to 100.375 Petajoules per annum. Change to proposal approved under S45c on 21 January 2025.