S45C changes to proposal

Title S45C changes to proposal Ministerial Statement Last updated
Coastal Walk Trail from Point Ann to Hamersley Inlet - Fitzgerald River National Park

Attachment 1 to Statement 884 – Two walk trails: an Eastern walk trail from Quoin Head to Cave Point including a spur trail to Hamersley Inlet; and a Western trail from Point Ann to Fitzgerald Inlet with shorter walk option at Lake Nameless; reduction and relocation of overnight camping, and amendment to Wilderness Management Zone Boundary – change to proposal approved under section 45C on 28 August 2012.

PDF icon Ministerial Statement 884 October 16, 2024
Roy Hill Infrastructure Railway

Attachment 1 to Statement 847 – Change to rail corridor alignment – change to proposal approved under s45C on 20 May 2011.

Attachment 2 to Statement 847 – Addition of a lateral access road extending outside the environmental approval corridor, and ancillary access roads within the environmental approval corridor – change to proposal approved under section 45C on 10 May 2013.

Attachment 3 to Statement 847 – Increase in the area of construction disturbance from 6,000 to 7,400 hectares – change to proposal approved under section 45C on 28 November 2013.

Please also refer to Ministerial Statement 864 for changed conditions.

Attachment 4 to Statement 847 – Excise of Rail Camp 2 (supporting infrastructure) from the development envelope (117.84 hectares). – change to proposal approved under section 45C on 20 October 2021.

Attachment 5 to Statement 847 - Amend proposal to remove reference to the “Roy Hill 1 Iron Ore Mining Project Stage 1 and 2” and allow transport of iron ore from third parties to
facilities at Port Hedland. Change approved on 27 November 2023.

Attachment 6 to Statement 847 - Amend proposal to allow for the construction and operation of the Hillside siding for loading and unloading of ore. Change approved under s. 45C on 10 October 2024.

PDF icon Statement 847.pdf October 10, 2024
Byford Rail Extension

Attachment 1 to Statement 1183 - Change to the extent of the development envelope and locations of disturbance footprint and change to Figure 1 and associated spatial data. Change approved under s. 45C on 10 October 2024.

PDF icon Statement 1183.pdf October 10, 2024
Utah Point Berth Project (Stage B)

Attachment 1 to Statement 788 - Removal of the references to Dust and Noise Suppression, and Stormwater Management from the Key Characteristics Table - change approved under s45C on 14 December 2015.

PDF icon Ministerial Statement 788 September 27, 2024
State Barrier Fence Esperance Extension

Attachment 1 to Statement 1095 - Change to the authorised extent of the development envelope within which clearing and disturbance can occur. Change to the authorised extent of existing firebreaks and previously uncleared areas within which ongoing chaining can occur. Change to conditions related to terrestrial fauna (western ground parrot (Pezoporus flaviventris)). Changes approved under s. 45C on 18  September 2024

PDF icon Ministerial Statement 1095.pdf September 18, 2024
Sodium Cyanide Plants (Liquid and Solid) at Kwinana and Transport of Sodium Cyanide by Road and Rail from Kwinana

Attachment 1 to Ministerial Statement 1196 - Amendment to the introduction, figures, schedule 1 and condition 1-1. Changes aproved under s. 45C on 27 August 2024.

PDF icon Statement 1196.pdf August 27, 2024
Browns Range Rare Earth Project

Attachment 1 to Ministerial Statement 986 - Revise the development envelope boundaries; and update Figures and reference to coordinates - change to proposal approved under section 45C on 12 April 2017.

Attachment 2 to Ministerial Statement 986 - Installation and operation of an Ore Sorting Circuit, resulting in higher radionuclide concentrations in sorted ore, intermediate process streams and the long-term storage of low-level radioactive waste (tailings). Change to proposal approved under section 45C on 4 September 2020.

Attachment 3 to Ministerial Statement 986 - Increase the disturbance footprint from 711 ha to 771 ha (8.4% increase) and an increase in the development envelope from 2,590 ha to 4,384 ha. Realignment of the development envelope and expansion of the borefield. Change to proposal approved under section 45C on 26 August 2024.

PDF icon Ministerial Statement 986.pdf August 26, 2024
Lumsden Point General Cargo Facility

Attachment 1 to Statement 967 - Include a 139.46 hectare development envelope for the temporary pipeline corridor; include DMMA B as a location for dewatering discharge; and update Figure 1 and delineation coordinates - change to proposal under s45C approved on 21 July 2017.

Attachment 2 to Statement 967 - Changes:

  • increase the dredging area development envelope by 6.9 ha to allow for deepening of the Stingray Creek Southern Swing Basin;
  • dredging volume increase by 400,000 m3 (total volume of 2.4 million m3); and
  • update Figure 1 and delineation coordinates.

Change to proposal under s45C approved on 14 April 2020.

Attachment 3 to Statement 967 -Changes:
• Include an increase to the causeway construction Development Envelope by 0.069 ha to allow for a straight path between DMMA C and the Land Backed Warf Area (total Development Area increase from 195.00 ha to 195.07 ha).
• Include an increase to average vertical dredge profile from 0.2 m to 0.5 m for berth pockets, shipping channel and turning basin dredging.
• Include onshore placement of remaining dredge material within Dredge Material Management Area C (DMMA C).- change to proposal under s45C approved on 27 September 2023.

PDF icon Ministerial Statement 967.pdf August 12, 2024
Western Extension to the Dardanup Mineral Sands Project to include the Burekup Mineral Sands Deposit

Attachment 1 to Statement 789 - Change to the Burekup West mine disturbance footprint area - section 45C change to proposal approved on 7 July 2010.

Attachment 2 to Statement 789 - Change to the Burekup West Mine disturbance footprint area – change to proposal approved under s45C on 8 July 2011.

PDF icon Ministerial Statement 789 - Western Extension to the Dardanup Mineral Sand s Project (Burekup Mineral Sand Project) June 28, 2024
Mineral sands mine, Dardanup (s46)

Attachment 1 to Statement 484 – Increase in disturbance area required for Tailings Pond – change to proposal approved under section 45C on 19 January 2004.

Attachment 2 to Statement 484 – Increase in maximum ore mining rate – change to proposal approved under section 45C on 28 June 2004.

Attachment 3 to Statement 484 – Multiple amendments to the Key Characteristics Table relating to project life, groundwater influence and water supply, as a result of the Dardanup Southern Extension Project – change to proposal approved under section 45C on 9 August 2012.

Attachment 4 to Statement 484 – Inclusion of the Waterloo Project into the Southern Extension – change to proposal approved under section 45C on 20 December 2013

PDF icon Ministerial Statement 484 June 28, 2024