Mining Area C - Southern Flank

Attachment 1 to Ministerial Statement 1072 - Changes:

  • a new location for managed aquifer recharge in the South Flank Valley
  • discharge to a drainage line that leads to Pebble Mouse Creek.

Changes to proposal approved under section 45c on 15 January 2020.

Attachment 2 to Ministerial Statement 1072 - Ministerial Statement Figure 4 to be replaced with a figure identifying the correct area for “Area A” due to an administrative error. Figure updated that accurately reflects areas of ‘Good’ to ‘Excellent’ condition native vegetation to be offset.

Changes to proposal approved under s.45c on 17 June 2025.

PDF icon Ministerial Statement 1072.pdf June 17, 2025
Duplication of synthetic rutile capacity, Capel

Attachment to Statement 291 - change to description in Consultative Environmental Review - approved on 18 August 2005.

Attachment to Statement 291 - change to description of Proposal in Consultative Environmental Review - approved on 3 October 2005.

PDF icon Ministerial Statement 291 April 7, 2025
Turkey Point Access Road and Bridge

Attachment 1 to Statement 1192 - Amendments to introduction, condition 1, figure and schedule 1. Change to statement approved under s. 45C on 5 September 2024.

Attachment 2 to Statement 1192 – Amendments to condition 1 (figure and schedule 1), condition 3-4 and the addition of a definition for Temporary construction causeway.  Changes to statement approved under s. 45C on 17 March 2025

PDF icon Statement 1192.pdf March 17, 2025
Alkimos Seawater Desalination Plant

Attachment 1 to Statement 1207 - Increase the proposal development envelope from 141.6 hectares (ha) to 142.73 ha. Decrease the marine development envelope from 11.45 ha to 11.42 ha. Increase the terrestrial development envelope from 130.15 ha to 131.31 ha. Proponent updates to the ‘Proposal Content Document’, as amended by the change to proposal approved under s.43A on 7 March 2023 to reflect the amendment approved under s.45C on 17 April 2024.Changes to conditions to reflect the change in the authorised extent of impacts. Change to conditions approved under s45C on 17 April 2024

Attachment 2 to Statement 1207 -  Increase the proposal development envelope from 142.73 hectares (ha) to 195.74 ha. Increase the terrestrial development envelope from 131.31 ha to 184.32 ha. Decrease the clearing of native vegetation from 51.20 ha to no more than 50.95 ha. Changes to conditions to reflect the change in the authorised extent of impacts to flora and vegetation, terrestrial fauna, and landform environmental values. Remove condition B1-2 and Figure 3 relating to the requirement for additional survey for Banksia attenuata woodlands over species rich dense shrublands (floristic community type 20a) threatened ecological community. Change to conditions approved under s45C on 21 January 2025.

Attachment 3 to Statement 1207 -  Increase the marine development envelope from 11.42 hectares (ha) to 77.79 ha.
• Change the outlet design from two 7 metre (m) diameter rosette diffusers to a single linear diffuser
• Change the definition of the Low Ecological Protection Area (LEPA) to accommodate the proposed change to the diffuser
• Change condition A1 to reduce the maximum salinity limit from 75,200 milligram per litre (mg/L) to 68,000 mg/L
• Decrease the maximum irreversible loss of benthic communities and habitats from 0.13 ha to 0.10 ha
• Increase the maximum disturbance to benthic communities and habitats from 8.39 ha to 8.68 ha
• Change the proposal description.. Change to conditions approved under s45C on 13 March 2025.

PDF icon Statement 1207.pdf March 13, 2025
Tutunup Titanium Minerals Mine

Attachment to Statement 621 - Change to description in Schedule 1 - change to proposal under s45C approved on 28 July 2005.

Attachment to Statement 621 - Change to description in Schedule 1 - change to proposal under s45C approved on 17 May 2006.

PDF icon Ministerial Statement 621 February 25, 2025
Extension Hill haematite haulage, road and rail siding

Attachment 1 to Statement 786 – Increased Rail Siding stockpile capacity and water use for dust suppression, and increased variability in train movements per day – change to proposal approved under section 45C on 14 February 2012.

Attachment 2 to Statement 786 – Removal of the General Description in Schedule 1, removal of the elements that are not key characteristics relevant to the environment, amendment to the element 'Vegetation Clearing' – change to proposal approved under section 45C on 10 March 2014.

PDF icon Ministerial Statement 786 January 29, 2025
Shine Iron Ore Project

Attachment 1 to Statement 940 - Reduce the development envelope from 646 ha to 595 ha. Change to proposal approved under S45c on 5 May 2020.

PDF icon Ministerial Statement 940.pdf January 29, 2025
Waitsia Gas Project Stage 2

Attachment 1 to Statement 1164 - Changes:

  • Increasing the development envelope from 354 hectares (ha) to 409.25 ha.
  • Increasing the disturbance footprint from 345 ha to 397.75 ha within the development envelope.

Changes to proposal approved under S45c on 4 October 2021.

Attachment 2 to Statement 1164 - Changing production facility capacity from 250 terajoules per day to an annual limit of 91.25 petajoules. Increasing the size of the development envelope from 409.25 ha to 580.9 ha. Increasing the number of wells from 8 to 19. Increasing the disturbance footprint from 397.75 ha to 479.2 ha. Change to proposal approved under S45c on 16 April 2024.

Attachment 4 to Statement 1164 - Increasing the size of the development envelope from 580.9 ha to 581.2 ha. Increasing the disturbance footprint from 479.2 ha to 479.6 ha within the
development envelope. Increasing the gas production facility capacity from 91.25 Petajoules per annum to 100.375 Petajoules per annum. Change to proposal approved under S45c on 21 January 2025.

PDF icon Statement 1164 January 21, 2025
Sorby Hills Silver Lead Zinc Project

Attachment 1 to Ministerial Statement 964 - Access road extension to the realigned Moonamang Rd. Inclusion of accommodation village. Revision of Figures 1-3. Changes approved under s45C on 20 June 2022.

Attachment 2 to Ministerial Statement 964 - An increase to the development envelope, and realignment of an access road.
• Addition of three new pits, expansion of pits, and increase the maximum pit depth.
• Removal of maximum excavation rate of ore, increase the construction timeframe, removal of maximum mineralised waste materials limit, increase to the storage volume of tailings, and change the tailings storage facility to an integrated waste landform.
• Increase to the dewatering limit.
• Increase to the maximum discharge limit and change the method of excess water disposal.
• Remove the minimum moisture content of ore concentrate.
• Amendment of the introduction of Ministerial Statement 964.
• Amendment of condition 6-1 of Ministerial Statement 964.
• Addition of condition 8 (Aboriginal Cultural Heritage) and condition 9 (Rehabilitation) to Ministerial Statement 964. Changes approved under s45C on 18 December 2024.

PDF icon Statement 964.pdf December 18, 2024
Sorby Hills Silver Lead Zinc Project (s46) [2170]

Attachment 1 to Ministerial Statement 1097 - Condition 3 is amended. Changes approved under s45C on 18 December 2024.