EPA Report Number:
1533
Key Environmental Factors:
Date published:
Tuesday, 18 November, 2014
Appeals close:
Tuesday, 2 December, 2014
Date of approval:
Tuesday, 10 March, 2015
Ministerial Statement:
S46C changes to conditions:
Attachment 2 to Statement 999 - Amendment to condition 14-2, approved under S46C on 4 January 2021.
Date S46C:
Monday, 4 January, 2021
s. 45C amendments:
Changes:
- Change the size of the Southern Infrastructure Corridor (SIC) development envelope from 12,003 ha to 5,465 ha. This involves:
- Reduction of the Southern Infrastructure Corridor development envelope by 6,668 hectares (ha).
- Addition of 130 ha to the Southern Infrastructure Corridor development envelope for the re-alignment of the power line and maintenance track.
- Update Figures 1, 2 and 5 and geographic coordinates as defined in Table 2 of Schedule 2.
Date of approval s. 45C:
Wednesday, 6 September, 2017