This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: November 25, 2024
Hamersley Iron Pty Limited (the proponent) propose to develop the Greater Paraburdoo Iron Ore Hub. The proposal is an expansion of the existing operations at Paraburdoo and Eastern Range which is not subject to a Ministerial Statement issued under Part IV of the, Environmental Protection Act 1986, (EP Act). The proposal area is located approximately six kilometres south of the town of Paraburdoo in the Pilbara region of Western Australia. Existing operations at Paraburdoo and Eastern Range are... Read more...Last updated: November 25, 2024
The Proposal is located in the Pilbara region of Western Australia within a development envelope of 20,821 ha and clearing no more than 1,564 ha. Onslow Infraco Pty Ltd (herein MRL a wholly owned subsidiary of Mineral Resources Limited) is proposing to develop: • A fully sealed private haul road, approximately 125km in length • Gas pipeline and ancillary haul road infrastructure. • Storage and bulk handling of ore at the Port of Ashburton. • Dredging a dedicated berthing pocket adjacent to the... Read more...Last updated: November 25, 2024
The construction of facilities for the development of the Greater Gorgon Gas Fields on the North-West Shelf, and the processing and export of the gas at a liquefied natural gas plant to be constructed on Barrow Island. Read more...Last updated: November 25, 2024
The construction of facilities for the development of the Pluto Gas Field on the North-West Shelf, and the processing and export of the gas at a liquefied natural gas plant to be constructed on the Burrup Peninsula. Extensive dredging will be undertaken adjacent to the export facility. Read more...Last updated: November 25, 2024
The Proposal is to construct and operate a 25 million tonne per annum Liquefied Natural Gas (LNG) facility and associated Domestic Gas (Domgas) facility in the proposed Ashburton North Strategic Industrial Area (ANSIA) 12 kilometres south west of the town of Onslow. Read more...Last updated: November 25, 2024
The proposal is to develop eight iron ore deposits at five locations, between 35 and 85 kilometres (km) south of Pannawonica. A heavy-haulage railway approximately 285 km in length would be developed to connect the mine area with a port to be constructed at Anketell Point, 25 km north-east of Karratha. The project would produce up to 30 million tonnes per annum (Mtpa) of iron ore. This Ministerial Statement was superseded by Statement 1026 and Statement 1027 published on 4 February 2016. Read more...Last updated: November 25, 2024
The Proposal is for the above and below water table mining of iron ore from five open cut pits, located approximately 30 km north of Nullagine. The Proposal includes the development of mine pits and associated infrastructure including but not limited to crushing and screening facilities, waste landforms, run of mine pad, access roads, solar field, administration, accommodation camp, stockpile and laydown areas, borrow pits, groundwater bores and transfer infrastructure, explosives magazine,... Read more...Last updated: November 24, 2024
Change the implementation conditions relating to greenhouse gas emissions Read more...Last updated: November 21, 2024
Proposal by the Water Corporation to renew a groundwater licence to continue abstraction from the Millstream aquifer of 6 gigalitres per annum (GL/a). The Water Corporation hold an existing temporary groundwater licence to abstract 3GL/a from the Millstream aquifer until February 2027 (GWL205069), enabling combined abstraction of up to 9GL/a. The referrer of the proposal contends that this significantly exceeds the Department of Water and Environmental Regulation’s sustainable limit of 6 GL/a,... Read more...Last updated: November 4, 2024
The Proposal is for the development of the Rhodes Ridge Iron Ore Project (the Proposal), located approximately 40 kilometres north-west of Newman, in the Shire of East Pilbara. The Proposal requires a disturbance footprint of up to 14,850 hectares within a 61,301 hectares Development Envelope. The Proposal includes the development of new above and below water table deposits, and associated activities. The proposal includes but is not limited to: development of new deposits including above and... Read more...Last updated: November 1, 2024
Alinta Energy (subsidiary of Alinta DEWAP Pty Ltd) currently owns and operates the existing Port Hedland Power Station (PHPS) located within the Boodarie Strategic Industrial Area approximately 12 km south of the Port Hedland town centre and approximately 5 km west of South Hedland, ., The Proposal utilises new technologies providing more energy efficient and reliable power to customers in the Port Hedland area. This will include the installation of a 60 Megawatts (MW) natural gas fuelled... Read more...Last updated: October 14, 2024
The Proposal occurs approximately 20 kilometres north of Karratha within an existing industrial area designated as a service corridor within the Burrup Strategic Industrial Area of the Burrup Peninsula. The Project involves the construction of a 550 meter pipeline and associated supporting infrastructure to transport a maximum of 150 TJ of natural gas per day from the Dampier to Bunbury Natural Gas Pipeline to the proposed Perdaman Urea Plant development. The key components of the Proposal... Read more...Last updated: October 10, 2024
The proposal is to construct and operate a railway of approximately 320 kilometres length and associated infrastructure to transport iron ore from the Roy Hill 1 Iron Ore Mining Project Stages 1 and 2 to facilities at Port Hedland. Read more...Last updated: September 27, 2024
The Utah Point Berth Project consists of two separate stages: Stage A: Dredging and Reclamation; and Stage B: Construction and Operation. Stage A, dredging and reclamation works for the UPBP was approved by the Minister for Environment as an amendment to the existing Fortescue Metals Group (FMG) approval and managed according to the approved conditions. The works for Stage A have been successfully completed. The EPA determined that Stage B, the construction and ongoing operation of stockyard... Read more...Last updated: August 12, 2024
The proposal is to develop and operate a general cargo facility within the Port Hedland inner harbour, within the Town of Port Hedland. This proposal has been superseded by the Lumsden Point General Cargo Facility Read more...Last updated: August 12, 2024
The proposal involves the dredging of not more than 6 million cubic metres (Mm3) of material for two new berth pockets and extensions to the existing departure channel and swing basin at Nelson Point to accommodate vessels of approximately 250,000 dead weight tonnes (DWT); disposal of dredged material at both offshore in Commonwealth waters site and to a land based dredged material management area (DMMA). This proposal has been superseded by the Lumsden Point General Cargo Facility Read more...Last updated: August 12, 2024
The proposal is to undertake dredging and construction to develop and operate a general cargo facility at Lumsden Point, located in Port Hedland. The proposal is a consolidation of the Nelson Point Dredging, RGP6 Port Development, Port Hedland and Lumsden Point General Cargo Facility approved proposals. Ministerial Statements 812 and 967 are now superseded. Read more...Last updated: July 15, 2024
Time limit for substantial commencement, review of the adequacy of existing implementation conditions to ensure consistency with the EPA’s current objectives for each environmental factor. Read more...Last updated: June 19, 2024
Buru Energy Limited proposes to build a 630km pipeline adjacent to the Great Northern Highway from Yulleroo (70 kms east of Broome) to Port Hedland, Western Australia (Figure 1). The pipeline will transport natural gas from proposed gas fields in the Canning Basin and tie-in to the Western Australian domestic gas network at Port Hedland. The project also includes up to four compressor / scraper stations, and four separate mainline valve locations. There will be provision for future off-takes to... Read more...Last updated: April 26, 2024
FMG Iron Bridge (Aust) Pty Ltd proposes to extend existing operations at its North Star Magnetite Project , which is subject to Ministerial Statement 993 issued under Part IV of the, Environmental Protection Act 1986 ., The proposal is located approximately 110km southeast of Port Hedland in the Pilbara region of Western Australia. The proposed extension includes increasing the Mining Development Envelope by 1425.9 ha and total clearing by 606.9 ha to support new mine pits (180.7 ha); an... Read more...