Attachment 1 to Statement 847 – Change to rail corridor alignment – change to proposal approved under s45C on 20 May 2011.
Attachment 2 to Statement 847 – Addition of a lateral access road extending outside the environmental approval corridor, and ancillary access roads within the environmental approval corridor – change to proposal approved under section 45C on 10 May 2013.
Attachment 3 to Statement 847 – Increase in the area of construction disturbance from 6,000 to 7,400 hectares – change to proposal approved under section 45C on 28 November 2013.
Please also refer to Ministerial Statement 864 for changed conditions.
Attachment 4 to Statement 847 – Excise of Rail Camp 2 (supporting infrastructure) from the development envelope (117.84 hectares). – change to proposal approved under section 45C on 20 October 2021.
Attachment 5 to Statement 847 - Amend proposal to remove reference to the “Roy Hill 1 Iron Ore Mining Project Stage 1 and 2” and allow transport of iron ore from third parties to
facilities at Port Hedland. Change approved on 27 November 2023.
Attachment 6 to Statement 847 - Amend proposal to allow for the construction and operation of the Hillside siding for loading and unloading of ore. Change approved under s. 45C on 10 October 2024.