Attachment 4 - Change to Schedule 6 (Summary of Proponent Offsets) – change to conditions approved under section 46C on 24 January 2011.
Attachment 1 - increment of Pluto LNG development project disturbance footprint to allow for minor infrastructure reconfiguration and realignment, and for the addition of security fencing required due to the facility being classified as a site of Vital National Importance - s45C change to proposal approved on 6 May 2008.
Attachment 2 - to include the construction of an Emergency Escape Route (walkpath) from Site B to Haul Road in the currently approved disturbance footprint of the proposal (as shown on Figure 5) - s45C change to proposal approved on 20 August 2009.
Attachment 3 - To increase the land disturbance footprint of the proposal by 3.03 hectares - change to proposal approved under s45C on 29 March 2010.
Attachment 5 - Changes:
- Deletion of the described gas field from the Proposal preamble, to clarify that gas from other fields can be processed at Pluto LNG (as per the Public Environmental Review);
- Deletion of the described gas turbine types used to drive the liquefaction compressors and for power generation from Schedule 1, to allow for greater flexibility in turbine design;
- Inclusion of gas export via shipping, trucking or piping to Schedule 1, to reflect the existence of the Pluto LNG trucking facility and proposed Pluto-North West Shelf Interconnector.
- Deletion of the described gas field Pluto North West Shelf from the Proposal Schedule 1 to gas fields.
Changes to proposal approved under section 45C on 1 July 2019.