This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: October 28, 2010
The proposal is to develop an iron ore mine at the Koolyanobbing Iron Ore Project-Mt Jackson J1 Deposit (Mt Jackson J1 Deposit), located approximately 110 kilometres (km) north-north-east of Southern Cross in the Shire of Yilgarn. The proposal includes two mine pits to extract approximately 33 million tonnes of iron ore and associated mining infrastructure. The proposed mine required disturbance of approximately 605 hectares (ha) of native vegetation for pits, associated mine infrastructure,... Read more...Last updated: September 17, 2010
The proposal is to construct and operate the Coolimba Power Station on a site located approximately 15 kilometres (km) south-south-west of Eneabba, and to establish an approximately 20 km long and 100 metre (m) wide infrastructure corridor that will accommodate the construction and operation of: a natural gas pipeline lateral to connect the power station to either the Dampier to Bunbury Natural Gas Pipeline (DBNGP) or the Parmelia Gas Pipeline; and a 330 kV electricity transmission line to... Read more...Last updated: June 30, 2010
The proposal is to construct and operate a minimum 50 GL/annum and up to 100 GL/annum desalination plant on Lots 32 and 33, and Part Lot 8 Taranto Road, Binningup; marine inlet/outlet pipes; and a water supply pipeline to transport potable water to the Integrated Water Supply Scheme via a storage facility near Harvey. Read more...Last updated: June 15, 2010
The strategic proposal is to: extend the Leeuwin Naturaliste National Park into the western part of Sussex Location 413; and develop the eastern part of Sussex Location 413 for tourism and residential purposes with associated public open space and foreshore reserves as generally depicted on the Development Guide Plan. Read more...Last updated: December 1, 2009
The proposal is to construct a deepwater port to service fully loaded Panamax sized vessels (65 000 DWT) at Oakajee, approximately 23 kilometres north of Geraldton. Three site locations (north, south and central) and two different design options (inshore and off-shore) were considered in developing the proposal. The design option favoured by the proponent is an in-shore port design at the northern sector. The port study area is approximately 23 kilometres north of Geraldton. The port will... Read more...Last updated: October 11, 2009
The proposal is to extend Roe Highway from South Street in Canning Vale to connect to Kwinana Freeway in Leeming over a distance of approximately 4.5 km. The highway is planned as a four-lane dual carriageway (two lanes in each direction), with provision for future upgrading to three lanes in each direction. The land required for any future upgrading will be provided in the median strip. The total footprint of the project area represents 62 hectares (ha). Approximately 53.9 ha of this area will... Read more...Last updated: March 13, 2009
The proposal involves the construction and operation of a 40 Megawatt power plant fuelled by up to 380,000 tonnes (+/-10%) per annum of, Eucalyptus globulus, (Bluegum) and pine plantation wastes, a pipeline for water supply, and a power line connecting the power plant to the sub-station. Read more...Last updated: February 12, 2009
The proposal is to develop an iron ore (haematite) mine at Jack Hills approximately 100 km west of Meekatharra. The project will have a lifespan of approximately seven years (five years of mining, two years of closure activities) and will be a contract mining operation. The project will consist of an open cut mine with one pit up to 140 metres deep (approximately 41.2 MT of ore and waste rock). The floor of the pit will be above the watertable and the pit will not be backfilled. Product will be... Read more...Last updated: December 17, 2008
The proposal is to develop a new iron ore mine approximately 60 kilometres west-north-west of Tom Price and 25 kilometres south-west of the existing Brockman 2 mine. The major components of the project include: Three new mine pits- with approximately 20% of the orebody occurring below the water table; Dry processing plant- including crushers, overland conveyor and screens; this will be located to the north of the pits running east/west to the rail loop; Associated mine infrastructure- this... Read more...Last updated: December 4, 2008
The construction and operation of a tourism development on Long Island, Wallabi Group, Houtman-Abrolhos Islands, consisting of visitor lodges (maximum of 60 guests), staff accommodation, communal facilities (including day-visitor facilities), boardwalks and gazebos, a swimming pool, deep water jetty, helipad, wastewater treatment plant, desalination plant and other maintenance/service facilities Read more...Last updated: August 5, 2008
To develop an open pit mine and process 20 million tonnes per annum (Mtpa) of ore to produce approximately 23,000 tonnes per annum (tpa) of molybdenum concentrate and approximately 48,000 tpa of copper concentrate. Read more...Last updated: March 20, 2008
The proposal is to establish materials stockpiling and handling facilities with a capacity of approximately 4 million tonnes at Cape Preston, approximately 60km west-south-west of Dampier. Read more...Last updated: July 12, 2007
The proposal is for the construction and operation of an ethanol bio-refinery on a 19 hectare site in the Kwinana Industrial Area. Read more...Last updated: November 29, 2006
This proposal is for the Development of Industrial Land on the Burrup Peninsula. The proposed site is designated Industrial Lease Area A (Site A). Approval would allow Woodside Energy Ltd to undertake limited site preparation activities for the future installation of infrastructure, such as LNG and condensate storage tanks, which would be needed should the proposed Pluto LNG Development be allowed to proceed. Read more...Last updated: November 17, 2006
The proposal is for the remaining life of the mine (50+ years), located west of Jimblebar Creek on Mining Lease 266SA. It entails increasing the iron ore production rate at the mine from 8 million tonnes per annum (Mtpa) to approximately 12Mtpa, and the mining of the currently undeveloped deposits on either side of the existing operation, including both in-situ hard rock and detrital ores. Approximately 600 million tonnes of Marra Mamba iron ore have been identified within the mining envelope.... Read more...Last updated: October 31, 2006
The proposal involves the construction and operation of an approximately 2.8 million tonnes per annum mineral sands mine and concentrator plant on part Swan Location 128, 354 & 508, Lot 2; part Swan Location 128 & 340, Lot 3; part Swan Location 128, 354, 355, 506, Lot 9; Swan Location 506; portion of each of Swan Locations 354 & 508, Lot 1 and part Swan Location 511 & 536, Lot 7, near the intersection of Brand Highway and Dewar Road, approximately 2.5 kilometres north-west of... Read more...Last updated: June 30, 2006
The proposal is to develop a mineral sand mine one kilometre north of the township of Waroona, which is approximately 140 km south of Perth. The area for assessment has been identified as Mining Tenements M70/735, M70/797 and M70/1089. Read more...Last updated: May 25, 2006
The proposal is for residential development on the East Clontarf site, approximately 18ha in size. The site is bounded by Manning Road, Centenary Avenue and the Canning River. It is zoned Urban in the Metropolitan Region Scheme (MRS) and Residential in the City of South Perth Town Planning Scheme. The foreshore area adjacent to the proposed development is identified for protection as Bush Forever site 333 and reserved for Parks and Recreation in the MRS. Read more...Last updated: May 17, 2006
The proposal is for the development of a titanium minerals mine at Tutunup, approximately 20 km east of Busselton. The proposal has the following main components: disturbance of 120 hectares of mainly cleared agricultural land; construction of water and fines dams, and topsoil, tails and overburden stockpiles; dewatering and mining, using dry mining techniques at up to two million tonnes per annum; abstraction of groundwater from the Yarragadee aquifer for process use; haulage of the Heavy... Read more...Last updated: April 28, 2006
The proposal is to reclaim a maximum of 3.5 hectares (ha) of Hanover Bay in Princess Royal Harbour to create a commercial and urban development along the Albany foreshore. This development involves tourist and residential accommodation, and industrial and maritime uses. As part of the development plan, it is proposed to provide services including drainage, sewerage, and connection to water mains and power. The foreshore redevelopment is part of a larger redevelopment plan for the Town of Albany. Read more...