Attachment 1 to Statement 717 – Redesign of approved mine site layout – plant, administration office, workshops, stacker reclaimer stockpiles, village, camp, waste dumps and stockpiles. Redesign of the rail spur. An increase in throughput from 20 to 22 megatonnes per year. An increase in water usage. The bitumen sealing of White Quartz Road. Removal of the conveyor and airstrip – change to proposal approved under section 45C on 19 September 2007.
Attachment 2 to Statement 717 – To change the route of the power line at its southern end to diverge from the rail infrastructure corridor and follow the Boolgeeda Valley and to change the power line capacity to 25 MW, operating at 33kV – change to proposal approved on 22 September 2008.
Attachment 3 to Statement 717– An increase in throughput from 22 to 42 megatonnes per year. Increase in waste dump height and additional locations. Plant, crusher, stockpiles, camp and village. An increase in water usage. Mine access road. Product transport route – change to proposal approved on 17 December 2008.