This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: April 29, 2024
The proponent, BHP Iron Ore Pty, proposes to increase power generation capacity at the existing Yarnima Power Station, approximately 2 kilometres north-west of Newman in the Pilbara. The proposal comprises an increase in installed firm power generation capacity from 154 megawatts up to 239 megawatts via installation of gas reciprocating engines and associated infrastructure. The gas reciprocating engines are proposed to be installed in stages up to a maximum of 120 megawatts (nominal).... Read more...Last updated: April 26, 2024
FMG Iron Bridge (Aust) Pty Ltd proposes to extend existing operations at its North Star Magnetite Project , which is subject to Ministerial Statement 993 issued under Part IV of the, Environmental Protection Act 1986 ., The proposal is located approximately 110km southeast of Port Hedland in the Pilbara region of Western Australia. The proposed extension includes increasing the Mining Development Envelope by 1425.9 ha and total clearing by 606.9 ha to support new mine pits (180.7 ha); an... Read more...Last updated: February 7, 2024
The Proposal is for the development of the Rhodes Ridge Iron Ore Project (the Proposal), located approximately 40 kilometres north-west of Newman, in the Shire of East Pilbara. The Proposal requires a disturbance footprint of up to 14,850 hectares within a 61,301 hectares Development Envelope. The Proposal includes the development of new above and below water table deposits, and associated activities. The proposal includes but is not limited to: development of new deposits including above and... Read more...Last updated: January 19, 2024
The Proposal includes the expansion and amalgamation of existing operations at: Jimblebar Iron Ore Revised Proposal (Ministerial Statement (MS 1126), Orebody 18 Iron Ore Mine (MS 439, MS 1012), Orebody 31 Iron Ore Mine (MS 1021), to include new above and below water table mining, overburden storage areas, beneficiation plant, overland conveyor, creek diversions, haul and access roads, pipelines and associated infrastructure. All mines and associated elements are proposed to be consolidated into... Read more...Last updated: December 22, 2023
Rio Tinto Winu Pty Limited (the Proponent) proposes to develop the Winu Project (the Proposal). The Proposal is a new copper-gold mine located approximately 300 km south of Broome and 320 km east of Port Hedland in the northern Pilbara region of Western Australia within both the Nyangumarta people’s and the Martu people’s Native Title Determination Areas. The Proposal conceptual footprint will require the clearing of up to 4,868 ha of native vegetation within a proposed 37,344 ha Development... Read more...Last updated: December 22, 2023
The Mulga Downs Hub and Rail Spur (the Proposal) is located approximately 210 km south of Port Hedland and 180 km northwest of Newman in the Pilbara region of Western Australia. The Proposal is for the development of a hub and rail spur to connect into the existing Roy Hill Railway for the transport of iron ore to Port Hedland. The Proposal includes truck unloading and train loading facilities, product rehandling facilities, stockyards, a laboratory, a rail loop and rail service tracks, lateral... Read more...Last updated: October 23, 2023
Port Hedland Green Steel Pty Ltd proposes to develop a large-scale downstream iron ore processing facility known as the Port Hedland Green Steel Project – Stage 1. The proposal is located in the Boodarie Strategic Industrial Area (BSIA) approximately 10 km south-west of Port Hedland in the Pilbara region. The proposal will consist of a pellet plant and a hot briquette iron (HBI) plant, consuming approximately 3 - 3.5 million tonnes per annum (Mtpa) of iron ore. Most of the pellets will be fed... Read more...Last updated: October 16, 2023
De Grey Mining Ltd proposes to construct and operate the Hemi Gold Project (the Project) located approximately 85 km south of Port Hedland, in the Pilbara Region of WA. The Project involves the excavation of open pits, mine dewatering, surplus water management including reinjection and controlled discharge. Associated supporting infrastructure includes an integrated waste landform tailings storage facility, waste rock landforms, low-grade stockpiles, airstrip, accommodation village, sealed... Read more...Last updated: September 8, 2023
BHP propose to expand existing mining operations at the Newman Hub in the Pilbara, approximately 2 kilometres (km) southwest of Newman. The Proposal is a derived proposal for mining operations at Newman (Western Ridge) authorised by the Pilbara Expansion Strategic Proposal, Ministerial Statement 1105. The proposal is to develop four iron ore deposits to expand BHP’s Newman Hub and includes: overburden storage areas ore and topsoil stockpiles haul and access roads overland conveyor 30 million... Read more...Last updated: September 8, 2023
The proposal is a derived proposal to expand existing mining operations at the Newman Hub in the Pilbara, previously authorised by Ministerial Statement (MS) 1105 Pilbara Expansion Strategic Proposal. This proponent proposes to expand the existing Orebody 32 above water table iron ore mine (currently authorised by MS 1037 Eastern Ridge Revised Proposal) in BHP’s Newman Hub to below the water table. The proposal is located 3.6 km northeast of Newman, and includes activities permitted to be... Read more...Last updated: August 14, 2023
Horizon Power is proposing to construct common user transmission infrastructure to enable the supply of grid electricity to the Burrup Strategic Industrial Area (SIA). The Proposal includes construction of an approximately 7 km long, 132 kV overhead transmission line between the Dampier substation and the Burrup SIA, clearing of unsealed access tracks along the transmission line route, an extension of the existing Dampier substation (inclusive of 132 kV switchgear, fencing and ancillary... Read more...Last updated: July 3, 2023
The proposal is to construct and operate an extension to the Dampier Cargo Wharf at the Port of Dampier. The proposal incorporates the construction of a new (adjoining) southern section of wharf and associated mooring dolphin, dredged berth pocket and vessel manoeuvring area. The Proposal will enable larger vessels (up to Panamax class) to access the terminal and facilitate new trades and products being handled at the Port. Key construction elements of the Project include dredging, blasting,... Read more...Last updated: June 26, 2023
Inquiry into implementation Condition 10 (Terrestrial and Marine Quarantine Management System), Condition 16 (Long-term Marine Turtle Management Plan) and Condition 25 (Coastal Stability Management and Monitoring Plan) to ensure that they are effective and reflect a contemporary outcome-based condition setting. It is noted a preceding Section 46 inquiry into Ministerial 800 (dated 11-03-2023) has been requested by the Minister for Environment in relation to Conditions 9, and 15 (Inquiry 1).... Read more...Last updated: June 26, 2023
Inquire into implementation Condition 9 (Quarantine Expert Panel) and Condition 15 (Marine Turtle Expert Panel) to ensure that they are effective and act as an independent advisory group for the Minister for Environment and the proponent on matters relating to terrestrial and marine quarantine and marine turtle monitoring and management. It is noted that a second Section 46 inquiry into Ministerial 800 (dated 11-04-2023) has also been requested by the Minister for Environment in relation to... Read more...Last updated: June 7, 2023
The Ridley Magnetite Project (the Proposal) is located approximately 57 km east of Port Hedland. The proposal is located within a 14,181 ha Development Envelope with an indicative disturbance footprint of 7,406 ha. The proposal is for the mining and processing of iron ore to produce 3 Million tonnes per annum (Mtpa) of magnetite concentrate for export under Stage 1, with an increase to 16.5 Mtpa under Stage 2. The proposal includes a single pit (below water table), run-of-mine pad, concentrate... Read more...Last updated: April 11, 2023
The proponent (Hamersley Iron Pty Limited) proposes to build and develop a desalination plant at Parker Point, Dampier, located approximately 2.5km north-east of the Dampier township. This Proposal will establish a reliable potable water supply for the Proponent’s Dampier port operation (including Parker Point and East Intercourse Island), Dampier town and connection into Water Corporation’s West Pilbara Water Supply Scheme (WPWSS). The desalination plant may be delivered in stages up to a... Read more...Last updated: January 9, 2023
The proposal is for the installation and operation of a Heated Overland Thermal Treatment (‘Hottpad’) system at t he Karratha liquid waste treatment plant and waste transfer station located approximately 6 kilometres south-west of Karratha. The Hottpad is intended to treat hydrocarbon-impacted ‘sludge’ from oil and gas operations in the region, that are currently transported interstate for thermal treatment. The proposal has a project life of 10 years and involves a self-sustaining smouldering... Read more...Last updated: October 31, 2022
The requested change relates to condition 3 of Statement 1055 for an extension to the time limit for proposal implementation. Read more...Last updated: July 11, 2022
The Proposal is located in the east Pilbara region of Western Australia within a development envelope of 718 ha and clearing no more than 270 ha. The Beatons Creek Gold Project is currently operating under relevant approvals and permits of the Environmental Protection Act (Part V) and Mining Act 1978 (Mining Act). The Fresh Rock Expansion proposes to mine deeper into the fresh rock resource including below the water table, enabling mining to continue at Beatons Creek. The proposal includes: •... Read more...Last updated: June 7, 2022
Alinta Energy Development Pty Ltd proposes to develop a 90 Mega Watts (MW) AC solar facility situated on Unallocated Crown Land near Alinta Energy’s existing Port Hedland Power Station located within the Boodarie Strategic Industrial Area. The proposal is located approximately 5 km south-west of South Hedland, adjacent to Great Northern Highway, within the Town of Port Hedland. The proposal consists of a 90 MW AC solar farm and a short (~2 km) transmission connection to the existing Port... Read more...