This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: January 21, 2025
Perdaman Chemicals and Fertilisers Pty Ltd intends to construct and operate a urea plant with a production capacity of approximately 2 million tonnes per annum (Mtpa) on Sites C and F within the Burrup Strategic Industrial Area (SIA) on the Burrup Peninsula. Both sites are located adjacent to the Murujuga National Park. The EPA considered the Study of the Cumulative Impacts of Air Emissions in the Murujuga Airshed in its assessment of the Perdaman Urea Project. Read more...Last updated: July 31, 2023
The proposal will provide additional port facilities at Port Hedland to receive and stockpile the product from emerging miners, specifically the various mines owned by the proponent’s shareholders, and load this product onto ships for export. Each of the shareholders is exploring and developing new iron ore projects in the Pilbara, with one company actively mining ore and exporting through the existing facilities in the Port of Port Hedland. The current shareholders of the proponent are Atlas... Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. Inquiry under s46 in response to a request to change condition 3 - Time Limit for Proposal Implementation of Ministerial Statement 891 . This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. Inquiry under s46 regarding amending the conditions of Ministerial Statement 858 . This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: February 2, 2022
Conditions 6-12, 9-1 to 9-5 inclusive, and 12-1 to 12-8 inclusive of Ministerial Statement 873 are to be removed from the statement and conditions 9-1 to 9-5 inclusive and conditions 12-1 to 12-8 inclusive are to be transferred into a new ministerial statement. The change will facilitate the transfer of conditions relevant to the operation of port facilities from Chevron Australia Pty Ltd to the Pilbara Ports Authority via this new Ministerial Statement. Read more...Last updated: August 12, 2020
The proposal is for dredging of not more than 3,500,000 cubic metres off Anderson Point, for a third ship berth; disposal of dredge spoil on preexisting and previously approved land at Anderson Point; and extension of the approved open-pile wharf. Read more...Last updated: March 6, 2019
Onslow Marine Support Base Pty Ltd is proposing to modify and extend the Beadon Creek harbour approach channel, turning basin and berth pocket as part of Stage 2 of the Onslow Marine Support Base (OMSB) proposal. The proposed capital dredging will enable offshore supply vessels to access the newly constructed OMSB land-backed wharf facility (Stage 1) within the Beadon Creek Maritime Facility. 930,000 cubic metres of dredge material will be disposed of onshore to a 44 hectare Dredge material... Read more...Last updated: June 11, 2018
The proposal is for the construction and operation of a technical ammonium nitrate production facility (TANPF) on Site D within the King Bay/Hearson Cove Industrial Estate on the Burrup Peninsula. The proposal is located approximately 13 kilometres north-west of Karratha. Read more...Last updated: August 31, 2016
Austeel Pty Ltd proposes to mine iron ore from the George Palmer Orebody on a pastoral lease about 25km south of Cape Preston. Ore will be fed to a purpose-built process plant to produce up to 13.8 million tonnes per annum of pellet iron and 4.7 million tonnes per annum of direct reduced iron (DRI) and/or hot briquetted iron (HBI). The products will be exported via a new port to be built at Cape Preston and Preston Island. Associated components comprise waste dumps, tailings storage facility,... Read more...Last updated: April 30, 2015
To expand the liquefied natural gas (LNG) production capacity of the existing proposal from 15 million tonnes per annum (Mtpa) to 20 Mtpa (nominal). Read more...Last updated: February 6, 2014
The proposal has the following main components: a 345 km railway line from Port Hedland to proposed mining operations at Mindy Mindy. This railway will be constructed in two parts: Part 1 from Port Hedland to the Chichester Ranges and Part 2 from the Chichester Ranges to Mindy Mindy; construction of port facilities consisting of rail loop, car dumper, stockyard and ore handling facilities (including two stackers and a single reclaimer), rescreening facility and product conveyor out to a wharf... Read more...Last updated: June 8, 1998
Proposal to develop a land-based marine shell breeding facility and residence on Downes Island approximately seven kilometres west of Port Hedland. Trochus shells (, Trochus niloticu, ), Pearl oysters (, Pteria penguin, ,, Pinctada margaritifera, ,, P. albina, ) and a range of other native Australian shells will be bred at the facility. Trochus and pearl oysters will be grown-out off-site. Read more...Last updated: June 25, 1996
The proposal is to construct and operate additional infrastructure to satisfy the requirements of the recently proposed AUSI Iron Project Direct Reduced Iron (DRI) plant near Wickham in the Pilbara region of Western Australia, the subject of EPA Bulletin 794. Read more...Last updated: November 21, 1995
Inquiry under s46 regarding amendment of conditions of Ministerial Statement 168 . The proposed changes involve the withdrawal of three conditions and consequential changes to three commitments from the 1991 statement. Onslow Salt submitted a final proposal in January 1995 (Onslow Salt Pty Ltd, 1995), which contained a detailed description and justification for the proposed changes. Read more...Last updated: October 25, 1991
Western Australian Petroleum Pty Ltd (WAPET) is operator for the participants in Exploration Permit No. TP/3 Part 1. WAPET has already drilled some 18 wells within the Permit Area, has developed the Saladin, Cowle and Yammaderry oilfields and is currently seeking approval to develop the Roller Oilfield. Over the next five year period, WAPET proposes to drill a further four to twelve exploratory wells within Permit Area TP/3 Part 1. Read more...