This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: November 6, 2023
Napier Corporation Pty Ltd (the proponent) is proposing to develop a pivot irrigation project to supply fodder crops for pastoral use. The proposal is situated within Napier Downs Pastoral lease (LPL N049855), located in the West Kimberley region, 240 km east northeast of Broome, Western Australia. The purpose of the proposal is the pivots will grow cattle fodder crops (Rhodes grass) for pastoral purposes use on Napier Downs Station, Mount-House Station and other Napier Corporation managed... Read more...Last updated: October 16, 2023
Water Corporation propose to conduct a 6- month water source abstraction trial to assess the long-term viability of a new water source for Walpole, Western Australia. The trial will be conducted during the summer peak water demand period and will use existing infrastructure. The source comprises three existing deep fractured rock bores located within the following Water Corporation Lots: • Bore 5/09 is located within the Swan Road road reserve • Bore 3/20 is located within part of Lot on Plan... Read more...Last updated: October 2, 2023
Bulletin Resources Limited are proposing a mineral exploration programme on exploration licence 74/655 within the Shire of Ravensthorpe. The proposal is within the Cocanarup Timber Reserve located to the west of the Ravensthorpe townsite. The proposal would include a total disturbance footprint of of 7 hectares for tracks and drill pads developed in two stages. Read more...Last updated: September 8, 2023
BHP propose to expand existing mining operations at the Newman Hub in the Pilbara, approximately 2 kilometres (km) southwest of Newman. The Proposal is a derived proposal for mining operations at Newman (Western Ridge) authorised by the Pilbara Expansion Strategic Proposal, Ministerial Statement 1105. The proposal is to develop four iron ore deposits to expand BHP’s Newman Hub and includes: overburden storage areas ore and topsoil stockpiles haul and access roads overland conveyor 30 million... Read more...Last updated: September 8, 2023
The proposal is a derived proposal to expand existing mining operations at the Newman Hub in the Pilbara, previously authorised by Ministerial Statement (MS) 1105 Pilbara Expansion Strategic Proposal. This proponent proposes to expand the existing Orebody 32 above water table iron ore mine (currently authorised by MS 1037 Eastern Ridge Revised Proposal) in BHP’s Newman Hub to below the water table. The proposal is located 3.6 km northeast of Newman, and includes activities permitted to be... Read more...Last updated: August 14, 2023
Horizon Power is proposing to construct common user transmission infrastructure to enable the supply of grid electricity to the Burrup Strategic Industrial Area (SIA). The Proposal includes construction of an approximately 7 km long, 132 kV overhead transmission line between the Dampier substation and the Burrup SIA, clearing of unsealed access tracks along the transmission line route, an extension of the existing Dampier substation (inclusive of 132 kV switchgear, fencing and ancillary... Read more...Last updated: July 3, 2023
The proposal is to construct and operate an extension to the Dampier Cargo Wharf at the Port of Dampier. The proposal incorporates the construction of a new (adjoining) southern section of wharf and associated mooring dolphin, dredged berth pocket and vessel manoeuvring area. The Proposal will enable larger vessels (up to Panamax class) to access the terminal and facilitate new trades and products being handled at the Port. Key construction elements of the Project include dredging, blasting,... Read more...Last updated: June 26, 2023
Inquiry into implementation Condition 10 (Terrestrial and Marine Quarantine Management System), Condition 16 (Long-term Marine Turtle Management Plan) and Condition 25 (Coastal Stability Management and Monitoring Plan) to ensure that they are effective and reflect a contemporary outcome-based condition setting. It is noted a preceding Section 46 inquiry into Ministerial 800 (dated 11-03-2023) has been requested by the Minister for Environment in relation to Conditions 9, and 15 (Inquiry 1).... Read more...Last updated: June 19, 2023
Woodside Energy Technologies Pty Ltd propose to construct and operate H2Perth, a domestic and export scale hydrogen and ammonia production facility, located approximately 40 km south of Perth. The proposal is to be located primarily within the Rockingham Industrial Zone (RIZ) in the City of Rockingham, with elements also located within the City of Kwinana and on the multi-user Kwinana Bulk Jetty. The proposal would produce approximately 3250 megawatts of gaseous hydrogen and approximately 3.25... Read more...Last updated: May 29, 2023
Time limit for substantial commencement, review of the adequacy of existing implementation conditions to ensure consistency with the EPA’s current objectives for each environmental factor. Read more...Last updated: May 15, 2023
The proposal is for extractive industry on Bussell Highway, Kudardup, in the Shire of Augusta Margaret River. The proposal is based on the Application for Development Approval, June 2020 (ADA) appended to the Shire of Augusta Margaret River’s Planning Approval / Consent No. P220293. The proponent has identified a reduced scope to only include extraction of sand from Cells 7, 8 and 9 (gravel extraction for cells 1,2,3,4,5 and 6 is excluded). All other activities within the ADA, including... Read more...Last updated: April 11, 2023
The proponent (Hamersley Iron Pty Limited) proposes to build and develop a desalination plant at Parker Point, Dampier, located approximately 2.5km north-east of the Dampier township. This Proposal will establish a reliable potable water supply for the Proponent’s Dampier port operation (including Parker Point and East Intercourse Island), Dampier town and connection into Water Corporation’s West Pilbara Water Supply Scheme (WPWSS). The desalination plant may be delivered in stages up to a... Read more...Last updated: March 27, 2023
Red Moon Property Holdings Pty Ltd and property lessee Altera Ltd propose to construct and operate Carpenter’s dam taking water from 4-mile brook. The proposal is to construct a dam not exceeding 3,400,000 cubic metres in capacity which includes an automatic bypass system that allows at least 8, 000 kilolitres of water to bypass the dam with excess water returned to the original watercourse. The proposal is in Beedelup, WA, approximately 20 kilometres Southwest of Manjimup, adjacent to the... Read more...Last updated: March 7, 2023
PSP Properties Pty Ltd propose to develop and operate a surf park at Lots 800 and Lot 9001 Prinsep Road, and Lot 801 Knock Way, Jandakot (City of Cockburn). The proposal includes development of an open water surfing lagoon, accommodation, food and beverage venues, function centre and events space, skating facilities, and health and wellness facilities. The proposal site is 5.78 hectares (ha) and is bound by industrial use areas to the north and south, the Kwinana Freeway to the west and remnant... Read more...Last updated: February 23, 2023
Buru Energy Ltd propose to undertake a 2D an d 3D geological survey at one site (Rafael patch) in the west Kimberley district, approximately 80 kilometres south of Derby. The proposal would include total disturbance of up to 438 hectares by raised blade clearing of 1147 km of seismic lines and construction of a temporary workers camp within an existing cleared well site. Read more...Last updated: February 20, 2023
Project Haber Pty Ltd proposes to construct and operate a 1.4 million tonnes per annum (Mtpa) urea plant in East Arrowsmith (South Erregulla). The proposal is located approximately 280 km north of Perth and 45 km south east of Dongara, in the Shire of Three Springs. The urea plant comprises of an Air Separation Unit (ASU) producing nitrogen, oxygen and hydrogen for various processes; an ammonia synthesis unit; and a granulation and urea production unit. Supporting infrastructure includes gas... Read more...Last updated: January 9, 2023
The proposal is for the installation and operation of a Heated Overland Thermal Treatment (‘Hottpad’) system at t he Karratha liquid waste treatment plant and waste transfer station located approximately 6 kilometres south-west of Karratha. The Hottpad is intended to treat hydrocarbon-impacted ‘sludge’ from oil and gas operations in the region, that are currently transported interstate for thermal treatment. The proposal has a project life of 10 years and involves a self-sustaining smouldering... Read more...Last updated: November 16, 2022
The Order of the Servants of Mary Incorporated proposes to develop Lot 9000 Wanneroo Road Sinagra for urban development. The urban development will include residential and commercial development, internal public road network, public open space, and drainage infrastructure. The development envelope for the proposal is 29.33 hectares, which includes 2.02 hectares conservation public open space. Read more...Last updated: October 31, 2022
The requested change relates to condition 3 of Statement 1055 for an extension to the time limit for proposal implementation. Read more...Last updated: August 29, 2022
TRECAP Pty Ltd proposes to amalgamate, clear and provide servicing of Lots 802, 804 and 4640 on Mandurah Road, East Rockingham to facilitate future industrial development, forming 4.0157 hectares (ha) in area. These lots are adjacent to the proponent’s Lot 850 (31.0840 ha) which is already used for industrial purposes. The site is within the Rockingham Industrial Zone strategic proposal area. The proponent has requested the EPA declare the proposal to be ‘derived proposal’; a proposal derived... Read more...