Attachment 1 to Statement 810 – Amendment to Condition 15 – change to proposal approved under s46C on 19 June 2011.
Attachment 2 to Statement 810 – Increase in proposal area to accommodate wet processing plant adjacent to the mining area, and change to area of vegetation to be protected – change to proposal approved under section 45C on 4 February 2013.
Attachment 3 to Statement 810 – Changes:
- Amend the approved mining area from 1379 hectares to 1532 hectares and include all of Lots 101, 103, 104 and 105 Westcott Road, Keysbrook.
- Relinquish several minor areas from the approved mining area totalling 7.2ha.
- Increase the Life of Mine from 8 to 9 years (approx.)
- Increase product quantity from 920,000 tonnes to 1,020,000 tonnes of heavy mineral concentrate.
- Amend the figures of MS 810 to include the Development Envelope and additional mining area.
Changes to proposal approved under section 45C on 14 October 2019.
Attachment 4 to Statement 810 – Amend the approved mining area from 1532 hectares to 1602 hectares and include an additional area on Lot 56 Westcott Road, Keysbrook. Increase the Life of Mine from 9 to 10 years. Increase product quantity from 1,020,000 tonnes to 1,070,000 tonnes of heavy mineral concentrate. Amend the figures of MS 810 to include additional mining area. Change to proposal approved under section 45C on 18 September 2023.
Attachment 5 to Statement 810 – Amend the approved mining area from 1602 hectares to 1744.3 hectares and include an additional area on Lot 63 Hopeland Road, Keysbrook. Increase the Life of Mine from 10 to 12 years. Increase product quantity from 1,070,000 tonnes to 1,135,000 tonnes of heavy mineral concentrate. Amend the figures of MS 810 to include additional mining area. Change to proposal approved under section 45C on 16 October 2023.