This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: November 25, 2024
Change the implementation conditions relating to greenhouse gas emissions Read more...Last updated: November 25, 2024
The construction of facilities for the development of the Pluto Gas Field on the North-West Shelf, and the processing and export of the gas at a liquefied natural gas plant to be constructed on the Burrup Peninsula. Extensive dredging will be undertaken adjacent to the export facility. Read more...Last updated: August 15, 2023
Inquire into and report on the matter of changing condition 12 of Ministerial Statement 757 to align it with contemporary greenhouse gas conditions reflecting the content of the Pluto LNG Facility Greenhouse Gas Abatement Program. Read more...Last updated: June 26, 2013
Chevron Australia Pty Ltd, as operator for the Gorgon Joint Venturers, proposes to extract, pipe, liquefy and export 10 million tonnes per annum of natural gas from the Greater Gorgon and Jansz gas fields using facilities offshore and on Barrow Island, Western Australia. Read more...Last updated: January 17, 2012
The proposal is to construct a sub sea pipeline, onshore gas treatment and compression plant, and sales gas pipeline. The subsea pipeline from the Macedon Gas Field (100 kilometres west of Onslow) connects to the onshore gas treatment and compression plant at Ashburton North (15 kilometres southwest of Onslow). The sales gas pipeline connects the onshore facility to the Dampier to Bunbury Natural Gas (DBNG) Pipeline. Read more...Last updated: January 19, 2011
Inquiry under s46 into a request to change the conditions of Ministerial Statement 757 . Read more...Last updated: November 29, 2006
This proposal is for the Development of Industrial Land on the Burrup Peninsula. The proposed site is designated Industrial Lease Area A (Site A). Approval would allow Woodside Energy Ltd to undertake limited site preparation activities for the future installation of infrastructure, such as LNG and condensate storage tanks, which would be needed should the proposed Pluto LNG Development be allowed to proceed. Read more...Last updated: June 29, 2006
The proponent proposes to construct and operate a number of looping sections adjacent (and connected) to the existing underground gas transmission pipeline within the DBNGP corridor. There are nine separate looping sections proposed from CS 1 south of Karratha, to CS 9, north of Gingin. Looping is a process of duplicating an existing pipeline between compressor stations for a certain distance. Once the specified distance is reached, it then ties back to the parallel pipeline. This design... Read more...Last updated: November 29, 2005
The proposal is to construct and operate a pipeline to supply gas to the Kemerton Power Station (located approximately 22km north east of Bunbury nearby the Kemerton Industrial Estate) and to construct a meter station at the power station site. The proposed pipeline would be 5km long and would connect to the DBNGP at MLV 154/155 and then run parallel to the existing DBNGP until it deviates west to supply the Kemerton Power Station. The proposed pipeline would be installed in the existing 16-... Read more...Last updated: July 14, 1998
The Proposal is to install a second undersea gas trunk line from the existing offshore Goodwin/North Rankin production platforms to a new terminal located in the existing onshore treatment plant at Withnell Bay on the Burrup Peninsula. Read more...