Attachment 1 to Statement 721 - Increase of dewatering to up to 25 GL/a, and reinjection to up to 18 GL/a - s45C change to proposal (as shown in Figure 4), approved on 25 September 2009.
Attachment 2 to Statement 721 - Amend the layout of the Cloud Break mine-site footprint (as shown in figure 5) and increase reinjection from 18 gigalitres to 20 gigalitres per annum - change to proposal approved under s45C on 12 July 2010.
Attachment 3 to Statement 721 – Increasing mine dewatering from 25 gigalitres per annum to 30 gigalitres and water injection from 20 gigalitres to 25 gigalitres and amend the annual rate of production – change to proposal approved under s45C on 10 June 2011.