EPA Report Number:
1597
Proponent documents:
Key Environmental Factors:
Date published:
Monday, 29 May, 2017
Appeals close:
Monday, 12 June, 2017
Date of approval:
Thursday, 12 October, 2017
Ministerial Statement:
s. 45C amendments:
Attachment 1 to Ministerial Statement 1065 - Increase in the development envelope to allow for laydown areas and pipe stringing; and a change in the alignment of the recharge pipeline and development envelope to allow for greater lengths of trenchless construction – change to proposal approved under s45C on 7 May 2018.
Attachment 2 to Ministerial Statement 1065:
Changes:
- modified location and alignment of the pipe being installed using trenchless technology including relocation of the two drill pits at either end of the 'trenchless technology' instalation
- addition of approximately 50 metres of pipe between the new trenchless technology installation and the approved alignment which will be constructed using open trench construction methods; and
- removal from the develpment envelope of approximately 385 metres (m) of pipe installation.
Change to proposal approved under s45C on 4 December 2018.
Date of approval s. 45C:
Monday, 7 May, 2018
Tuesday, 4 December, 2018