EPA Report Number:
1651
Key Environmental Factors:
Date published:
Monday, 14 October, 2019
Appeals close:
Monday, 28 October, 2019
Date of approval:
Thursday, 21 November, 2019
Ministerial Statement:
s. 45C amendments:
Attachment 1 to Statement 1118 - Changes:
• Addition of a water supply pipeline between Moorine Rock and the Earl Grey Lithium Project
• Change to the Development Envelope to accommodate pipeline infrastructure
• Amendment to the total footprint but no additional clearing.
Changes approvd undr S45c on 18 May 2021.
Date of approval s. 45C:
Tuesday, 18 May, 2021