This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: August 4, 2025
The Ridley Magnetite Project (the Proposal) is located approximately 57 km east of Port Hedland. The Proposal is located within a 19,102 ha Development Envelope (DE) with an indicative disturbance footprint (IF) of 8,484 ha. The Proposal is for the mining and processing of iron ore to produce up to 16.5 million tonnes per annum (Mtpa) of magnetite concentrate. The Proposal includes a single pit (below water table), run-of-mine pad, concentrate stockpiles, laydown areas, waste dumps,... Read more...Last updated: July 4, 2025
Conditions 6-12, 9-1 to 9-5 inclusive, and 12-1 to 12-8 inclusive of Ministerial Statement 873 are to be removed from the statement and conditions 9-1 to 9-5 inclusive and conditions 12-1 to 12-8 inclusive are to be transferred into a new ministerial statement. The change will facilitate the transfer of conditions relevant to the operation of port facilities from Chevron Australia Pty Ltd to the Pilbara Ports Authority via this new Ministerial Statement. Read more...Last updated: June 13, 2025
K plus S Salt Australia Pty Ltd is seeking approval to construct and operate a 3.5 million tonnes per annum (Mtpa) Solar Salt Project located approximately 40 km south-west of the township of Onslow, within the Shire of Ashburton. Read more...Last updated: January 21, 2025
Perdaman Chemicals and Fertilisers Pty Ltd intends to construct and operate a urea plant with a production capacity of approximately 2 million tonnes per annum (Mtpa) on Sites C and F within the Burrup Strategic Industrial Area (SIA) on the Burrup Peninsula. Both sites are located adjacent to the Murujuga National Park. The EPA considered the Study of the Cumulative Impacts of Air Emissions in the Murujuga Airshed in its assessment of the Perdaman Urea Project. Read more...