Condition 3-1 of Ministerial Statement 906 requires the proponent to substantially commence the proposal within five years of the date of issue of the Statement (that is, before 1 August 2017). The proposal has not yet substantially commenced.
The proponent for the proposal, Point Grey Development Company Pty Ltd, has requested an extension of the Time Limit of Authorisation (now referred to as “Time Limit for Proposal Implementation”) for substantial commencement to be extended to be consistent with the Commonwealth approval timeframe, to 28 June 2019.