This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: December 5, 2005
The proposal is to expand Hamersley Iron's iron ore operations at Dampier Port from 95 million tonnes per annum (Mtpa) to 120 Mtpa. The Hamersley Iron Dampier Port operations include rail and port facilities, rail maintenance workshops, a 120MW power station, laboratories and other service and administrative functions. The port operations are located at two terminals – Parker Point (PP) and East Intercourse Island (EII). The proposal is to increase the capacity of the Parker Point terminal... Read more...Last updated: October 28, 2005
The construction of a gas pipeline to supply natural gas for on-site power generation at Nifty Copper Operations located in the eastern Pilbara region. The gas pipeline is a 46 kilometre spur line from the Port Hedland - Telfer Pipeline to Nifty Copper Operations. Inquiry under s46 to change implementation conditions of Ministerial Statement 676 . Read more...Last updated: October 25, 2005
The proposal is for the construction of a gas pipeline to supply natural gas for on-site power generation at Nifty Copper Operations located in the eastern Pilbara region. The gas pipeline is a 46 kilometre spur line from the Port Hedland - Telfer Pipeline to Nifty Copper Operations. Read more...Last updated: October 12, 2005
The proposal is to construct an ammonia–urea plant on the Burrup Peninsula. The plant will have a production capacity of 2300 tonnes/day (t/d) of ammonia and 3500 t/d of urea. The plant and associated infrastructure will be composed of: a natural gas supply pipeline from the North West Shelf Liquefied Natural Gas (LNG) Plant (to be located in a multi-user service corridor); ammonia plant; urea plant; fluid bed granulation plant; seawater desalination, treatment and storage; internal power... Read more...Last updated: October 3, 2005
The proponent wishes to split the original proposal into two proposals, an ammonia plant and a urea plant. The approval to split the proposal was granted as a change to the proposal on 12 October 2005 under section 45C of the, Environmental Protection Act 1986, . The split of the proposal is based on commercial grounds and there are no changes to the capacities or other operational characteristics of the proposal as originally approved. The split of the proposal will result in each plant being... Read more...Last updated: September 5, 2005
Proposal by Hamersley Iron Pty Limited (Hamersley), the proponent, to mine a section of the Yandicoogina Channel Iron Deposit (CID). Read more...Last updated: August 25, 2005
The proposed Simpson Development proposal will make use of three existing wells and one that is the subject of a separate referral. The development will consist of: the Simpson Alpha offshore mini-platform located at the Tanami-4 and Tanami-5 wells surface location; the Simpson Bravo offshore mini-platform located at the Simpson-1 and Simpson-3H well locations; and a sub-sea pipeline bundle linking the two mini-platforms to each other and to existing facilities on Varanus Island. The pipeline... Read more...