This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: November 9, 2020
NW Interconnected Power Pty Ltd (the Proponent) is seeking to revise its approved proposal to develop the Asian Renewable Energy Hub. The proposal was previously referred under section 38 of the Environmental Protection Act 1986 (EP Act), assessed by the Environmental Protection Authority (EPA) at the level of Public Environmental Review (PER) (NW Interconnected Power 2019), and subsequently approved by the Western Australian Minister for Environment in October 2020. This referral is for ... Read more...Last updated: July 23, 2020
Change to condition 1 commitment 39 of Ministerial Statement 308 in order to consider the change of distance to the nearest sensitive receptor. Read more...Last updated: May 27, 2020
Changes to conditions 3-1 and 3-2, time limit of authorisation of Ministerial Statement 985 in order to extend the Time Limit of Authorisation. Read more...Last updated: April 20, 2020
The Department of Transport is proposing to construct and operate the Port Hedland Spoilbank Marina Proposal, including marine and land-based components within the Town of Port Hedland, Pilbara, WA. The Proposal includes: marina basin, mooring facilities (up to 80 pens), boat launching area, sand trap and entrance channel capital dredging works resulting in up to 900,000 cubic metres (m3) of dredge spoil and dredged to a maximum depth of -2m chart datum (-6m AHD). Dredge spoil will be used... Read more...Last updated: April 6, 2020
Hamersley Iron Pty Limited propose to expand its existing Brockman 4 Syncline Iron Ore Mine. The expansion would include further clearing of up to 4,800 hectares and expand its current development envelope by 2,567 hectares. Additional dewatering would also take place resulting in dewater discharge extending further along Boolgeeda Creek by nine kilometres. Read more...Last updated: January 15, 2020
The proposal is to revise the Mining Area C operation (located approximately 90km WNW of Newman) to include a new satellite ore body which is located approximately 8 km to the south of the existing approved Mining Area C operations. The revised proposal would require the additional clearing of approximately 19,850 hectares of vegetation and mining below the water table. Read more...