Pinjarra Refinery Efficiency Upgrade

Project
Proposal description

The proposal is to upgrade the Pinjarra Alumina Refinery. The proposal involves an upgrading of the seed filtration facility to improve its efficiency in order to increase the alumina production by approximately 17% to approximately 4.2 million tonnes per annum. This will require an increase in the bauxite mining rate at Alcoa’s Huntly bauxite mine and additional bauxite grinding, slurry storage and calcination facilities.

Assessment Number
1498
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
1. Referral
2. Decision on whether to assess this proposal
Preliminary Environmental Factors
Date published
3. Assessment
Environmental Review
4. EPA Report on assessment
EPA Report Number
1122
Key Environmental Factors
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Post-assessment changes
s. 45C amendments

Attachment 1 to Statement 646 - Amendment of Key Proposal Characteristics: Atmospheric emissions from 640 tpa NOx to 780 tpa NOx - change to proposal approved under s45C on 1 July 2008.

Attachment 2 to Statement 646 - Increase in production, bauxite residue generation, emissions of NOx, CO and greenhouse gases; update description of the proposal including the ‘Development Envelope’; correction of a unit error; and removal of elements that are not key proposal characteristics relevant to the environment, managed under other legislation, completed, or not relevant to the proposal - change to proposal approved under s45C on 21 September 2015.

Date of approval s. 45C