Fimiston Gold Mine Operations Extension Stage 3 and Mine Closure Planning

Project
Proposal description

This report provides the Environmental Protection Authority's (EPA's) advice and recommendations to the Minister for the Environment on the proposal by Kalgoorlie Consolidated Gold Mines Pty Ltd (KCGM) to expand their Fimiston operations in Kalgoorlie by widening and deepening the Superpit by means of the Golden Pike Cutback, and to plan for mine closure.

Assessment Number
1581
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Date published
3. Assessment
Scoping
Environmental scoping document for public comment
Environmental Review
Environmental Review documentation
Proponent response to submissions
4. EPA Report on assessment
EPA Report Number
1270
5. Decision on proposal and implementation of proposal
Ministerial Statement
Comments

The continuation of mining operations at the Fimiston site, and expansion and deepening of the Superpit to 600 metres via the Golden Pike Cutback. Additional waste dumps will be created to the north of the pit to contain 140 million tonnes of waste rock. The Fimiston I and II tailings storage facilities and/or the Kaltails tailings storage facility will be expanded to contain the additional tailings.

Date of approval
Post-assessment changes
S46C changes to conditions

Attachment 2 to Statement 782 – Replacement of condition 11-3 – change to proposal approved under section 46C on 23 July 2013.

Date S46C
s. 45C amendments

Attachment 1 to Statement 782 – Clearing for Kaltails tailings storage facility, contingency clearing for infrastructure post Kaltails recommissioning, and inclusion of hydrogen peroxide dosing facility – change to proposal approved under s45C on 6 September 2010.

Attachment 3 to Statement 782 – Removal of different options for management of tailings in the description of the proposal; updated description of the proposal including the ‘Proposal footprint’ and ‘Mine Development Envelope’; and removal of elements that are not key proposal characteristics relevant to the environment or managed under other legislation – change to proposal approved under section 45C on 17 June 2015.

Date of approval s. 45C