EPA Report Number:
1357
Proponent documents:
Date published:
Monday, 10 May, 2010
Appeals close:
Monday, 24 May, 2010
Date of approval:
Thursday, 30 September, 2010
Ministerial Statement:
Notice of Interim Implementation Conditions under Section 46A :
Date of approval (46a):
Thursday, 19 May, 2011
Section 46 inquiry:
s. 45C amendments:
Attachment 1 – Change to the Tug Harbour Extension dredging footprint area (i.e. updated Table 4 and Figures 2, 4b and 4c) – change to proposal approved under s45C on 12 May 2011.
Attachment 3 – Additional dredging – increase in “large dredge area” and “tug harbour dredge area” (replaced Figure 5, Table 4 and Key Characteristics Table – change to proposal approved under s45C on 22 December 2011.
Attachment 4 – Additional clearing – additional 46 ha of terrestrial clearing. Inclusion of figure 7 depicting Terrestrial Component of the Proposed Footprint – change to proposal approved under s45C on 28 March 2012.
Date of approval s. 45C:
Thursday, 12 May, 2011
Thursday, 22 December, 2011
Wednesday, 28 March, 2012
Note: A change to condition 8-1 of Ministerial Statement 840 was approved by the Minister for Environment on 31 October 2011 in Ministerial Statement 876.