This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: February 9, 2024
The proposal includes the existing Cloudbreak iron ore mine and proposed expansion. The existing mine includes open pit strip mining, backfilling of pits, progressive rehabilitation and ore processing. The expansion includes increasing ore production, development of new pits and permanent waste landforms, the development of new infrastructure, additional dewatering and water disposal activities, an upgrade of the ore processing facility. Read more...Last updated: December 15, 2023
Z1Z Resorts Pty Ltd proposes to redevelop the Ningaloo Lighthouse Holiday Park, located along Yardie Creek Road, North West Cape. The Proposal comprises the construction of new visitor accommodation; the construction of associated ancillary facilities (i.e., staff accommodation, power supply infrastructure, water supply and treatment, wastewater treatment and reuse, and replacement service station (vehicle refuelling) etc.); refurbishment of the Vlamingh Head Lighthouse Quarters (a part of... Read more...Last updated: July 31, 2023
The proposal will provide additional port facilities at Port Hedland to receive and stockpile the product from emerging miners, specifically the various mines owned by the proponent’s shareholders, and load this product onto ships for export. Each of the shareholders is exploring and developing new iron ore projects in the Pilbara, with one company actively mining ore and exporting through the existing facilities in the Port of Port Hedland. The current shareholders of the proponent are Atlas... Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. Inquiry under s46 in response to a request to change condition 3 - Time Limit for Proposal Implementation of Ministerial Statement 891 . This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: July 3, 2023
The Proposal is located in the Pilbara region of Western Australia within a development envelope of 20,821 ha and clearing no more than 1,564 ha. Onslow Infraco Pty Ltd (herein MRL a wholly owned subsidiary of Mineral Resources Limited) is proposing to develop: • A fully sealed private haul road, approximately 125km in length • Gas pipeline and ancillary haul road infrastructure. • Storage and bulk handling of ore at the Port of Ashburton. • Dredging a dedicated berthing pocket adjacent to the... Read more...Last updated: August 14, 2019
Fortescue Metals Group Limited proposes to build a 120 km railway linking their existing Solomon Mine with their proposed Eliwana Iron Ore Mine, located 90 km west-northwest of Tom Price (Shire of Ashburton). The eastern section of the proposed Eliwana Railway Project development envelope is adjacent to Karijini National Park. Proposed Infrastructure within the Rail Development Envelope includes: Railway and associated embankment; Rail loop; Crossing/passing loops; Railway overpass; Train... Read more...Last updated: July 1, 2019
The construction of facilities for the development of the Pluto Gas Field on the North-West Shelf, and the processing and export of the gas at a liquefied natural gas plant to be constructed on the Burrup Peninsula. Extensive dredging will be undertaken adjacent to the export facility. Read more...Last updated: November 12, 2018
The proposal is to develop and operate an iron ore mine approximately 50 km west-northwest of Paraburdoo, Western Australia, a 20 km long gas pipeline corridor, and a 150 km long rail transport corridor that would connect the proposed mine to the West Pilbara Iron Ore Project Stage 1 infrastructure. Read more...Last updated: November 23, 2016
The Minister for Environment has requested that the Environmental Protection Authority (EPA) inquire into and report on the matter of changing the implementation conditions of Ministerial Statement 741 and Ministerial Statement 840 relating to dust and noise regulation for Cape Lambert Port A and B development proposals under s46 of the EP Act. Read more...Last updated: March 3, 2016
The proposal includes the existing Hamersley Yandicoogina iron ore project and proposed expansion. The existing project includes open pit mining at the Junction Central and Junction South East operations and associated infrastructure, dewatering activities, closure and rehabilitation. The expansion includes the development of new pits at Junction South West and Oxbow, temporary waste landforms, the development of new infrastructure, additional dewatering and water disposal activities. The... Read more...Last updated: February 4, 2016
The proposal is to develop eight iron ore deposits at five locations, between 35 and 85 kilometres (km) south of Pannawonica. A heavy-haulage railway approximately 285 km in length would be developed to connect the mine area with a port to be constructed at Anketell Point, 25 km north-east of Karratha. The project would produce up to 30 million tonnes per annum (Mtpa) of iron ore. Read more...Last updated: December 14, 2015
The Utah Point Berth Project consists of two separate stages: Stage A: Dredging and Reclamation; and Stage B: Construction and Operation. Stage A, dredging and reclamation works for the UPBP was approved by the Minister for Environment as an amendment to the existing Fortescue Metals Group (FMG) approval and managed according to the approved conditions. The works for Stage A have been successfully completed. The EPA determined that Stage B, the construction and ongoing operation of stockyard... Read more...Last updated: August 7, 2015
The Minister for Environment requested the EPA inquire into the matter of changing the implementation conditions relating to the Orebody 18 Iron Ore Mine proposal, particularly the matter of setting a condition on the proposal that would require environmental offsets for the clearing of native vegetation. Inquiry under s46 relating to Ministerial Statement 439 and EPA Report 840 . Read more...Last updated: August 5, 2015
The proposal is to construct and operate an ammonia plant on the Burrup Peninsula, approximately 1300 kilometres north of Perth. The selected project site is located in the King Bay-Hearson Cove Industrial Area and is approximately 6 and 10 kilometres from the towns of Dampier and Karratha respectively. The site covers an area of about 72 hectares and the actual plant footprint and infrastructure (including a thermal desalination plant) will occupy an area of approximately 20 hectares. Read more...Last updated: October 15, 2014
Fortescue Metals Group Limited (Fortescue) proposes to develop two new mines within the Solomon Project, a greenfield site approximately 60 kilometres (km) north of Tom Price and adjacent to the North Eastern boundary of the Karijini National Park, and to construct a 127 km railway from the new mines eastwards to the existing Fortescue railway. Read more...Last updated: February 6, 2014
The proposal has the following main components: a 345 km railway line from Port Hedland to proposed mining operations at Mindy Mindy. This railway will be constructed in two parts: Part 1 from Port Hedland to the Chichester Ranges and Part 2 from the Chichester Ranges to Mindy Mindy; construction of port facilities consisting of rail loop, car dumper, stockyard and ore handling facilities (including two stackers and a single reclaimer), rescreening facility and product conveyor out to a wharf... Read more...Last updated: January 30, 2013
The proposal is to construct and operate a multi-user deep-water port with iron ore stockpiling, transfer and ship loading facilities and ancillary infrastructure at Anketell Point. The proposal allows for facilities required by the Proponent and future third parties to be developed. Read more...Last updated: January 11, 2013
Brockman Iron Pty Ltd is proposing to construct a railway line and associated infrastructure in the Hamersley Iron province in the Pilbara region of Western Australia, approximately 100 kilometres (km) north west of Newman. The railway line would be approximately 79 km in length. The proposal will connect the previously approved Brockman Marillana Iron Ore Project ( Ministerial Statement 855 ) to the existing Fortescue Metals Group (FMG) railway line. Read more...Last updated: June 19, 2012
The proposal is to construct and operate approximately 70 km of duplicate rail line and supporting infrastructure from the Cape Lambert Port facilities to Emu Siding. Read more...Last updated: February 28, 2012
The proposal is to construct and operate the Outer Harbour Development which includes landside and marine infrastructure for the handling and export of iron ore from BHPBIO’s operations. The Boodarie stockyard infrastructure will supply an overland conveyor to a transfer pad located to the west of the existing Finucane Island facilities. A piled jetty will transfer ore material to the ship loaders located at the piled wharf. Read more...