EPA Western Australia
Published on EPA Western Australia (https://www.epa.wa.gov.au)

Home > Printer-friendly > Printer-friendly > Albemarle Kemerton Plant

Albemarle Kemerton Plant

Project
Proponent: 
Albemarle Lithium Pty Ltd
Proposal description: 

Albemarle Lithium Pty Ltd (Albemarle) is proposing to stablish the Albemarle Kemerton Plant, a Lithium hydroxide Product manufacturing plant and associated infrastructure, within the Kemerton Strategic Industrial Area (KSIA), approximately 17 kilometres north-east of Bunbury.

The Albemarle Kemerton Plant will produce up to 100,000 tonne per annum (tpa) of lithium hydroxide monohydrate (Lithium Hydroxide Product)  from five 20,000 tpa process trains and produce up to 1,100,000 tpa of tailings.

The construction of these trains will be staged over the next ten years with construction of the first trains planned to commence in 2018.  The plant will process spodumene ore concentrate supplied from the Talison mine in Greenbushes, the biggest source of spodumene ore concentrate in the southern hemisphere.

Assessment Number: 
2153
Region: 
South West
Referred under EP Act: 
s38
Industry sector: 
Industrial
Last updated: 
February 3, 2026
Related EPA Media Statement: 
EPA recommends approval for South West lithium manufacturing plant
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment on this referral: 
Albemarle Kemerton Plant
Comment period: 
Monday, 20 November, 2017 to Sunday, 26 November, 2017
Referral documentation: 
PDF icon Referral Form
PDF icon Appendix A - Albemarle Kemerton Plant Material Safety Data Sheets
PDF icon Appendix B - Best Available Techniques Benchmarking
PDF icon Appendix C - Stormwater Drainage System
PDF icon Appendix D - Ecological Australia Technical Reports (1)
PDF icon Appendix D - Ecological Australia Technical Reports (2)
PDF icon Appendix D - Ecological Australia Technical Reports (3)
PDF icon Appendix E - Additional Area Biological Assessment
PDF icon Appendix F - Air Quality Impact Assessment Part A
PDF icon Appendix F - Air Quality Impact Assessment Part B
PDF icon Appendix G - Noise and Vibration Assessment
PDF icon Appendix H - Environmental Management Plan
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Additional Assessment Information (public review)
Extract of determination: 
PDF icon Albemarle Kemerton Plant
Preliminary Environmental Factors: 
Social Surroundings
Flora and Vegetation
Terrestrial Environmental Quality
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Tuesday, 20 February, 2018
4. EPA Report on assessment
EPA Report Number: 
1618
EPA Report: 
PDF icon EPA Report 1618 - Albemarle Kemerton Plant - EPA Report and Recommendations
Key Environmental Factors: 
Flora and Vegetation
Terrestrial Environmental Quality
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Friday, 15 June, 2018
Appeals close: 
Friday, 29 June, 2018
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Friday, 26 October, 2018
Ministerial Statement: 
PDF icon Statement 1085.pdf
Post-assessment changes
Section 46 inquiry: 
Albemarle Kemerton Plant (s46) [2490]
s. 45C amendments: 

Attachment 1 to Statement 1085 - change to conditions approved under S45c 14 March 2022.

Attachment 2 to Statement 1085 - Administrative change to correct a misdescription to and to the format of implementation condition 8 that does not alter the obligations of the proponent. Change to conditions approved under S45c on 3 February 2026.

Attachments: 
PDF icon Attachment 2 - Notice and Summary of Reasons.pdf
Date of approval s. 45C: 
Monday, 14 March, 2022
Tuesday, 3 February, 2026

Source URL:https://www.epa.wa.gov.au/proposals/albemarle-kemerton-plant