Phillips River Gold Project

Project
Proponent: 
Tectonic Resources NL
Proposal description: 

The proposal is for the developing of mining operations at the areas of Trilogy and Kundip, construction of a haul road, construction and operation of a processing plant, and disposal of tailings at the RAV 8 site.

Assessment Number: 
1618
Region: 
Goldfields Esperance
Referred under EP Act: 
s38
Industry sector: 
Gold
Last updated: 
March 28, 2006
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Referral documentation: 
PDF icon Environmental Protection Statement (December 2005)
Package icon Appendix A Letters from Shire and Landowners
PDF icon Appendix B GCA - Geochemical Characterisation- Kundip and Trilogy
PDF icon Appendix C OES - Topsoil Characterisation at Kundip and Trilogy
PDF icon Appendix D Hydrology and surface water quality
PDF icon Appendix E Hydrology and groundwater
PDF icon Appendix F Vegetation and Flora
PDF icon Appendix G OES - Trilogy Baseline Flora survey
PDF icon Appendix H Fauna studies and decision on MNES
PDF icon Appendix I Brad Goode Aboriginal Heritage Survey
PDF icon Appendix J Tamora - Aboriginal Heritage Survey
Package icon Appendix K Department of Indigenous Affairs correspondence
PDF icon Appendix L Correspondence to and from the Heritage Council of WA
PDF icon Appendix M Process Facility
PDF icon Appendix N SRE Tailings Storage Facility NOI
PDF icon Appendix O Preliminary Geotechnical Assessment (slope design parameters)
PDF icon Appendix P Adjustments to wall design parameters
PDF icon Appendix Q Geochemical Characteristics Process Tailings Slurry
PDF icon Appendix R SRE Trilogy Water Storage Facility NOI
PDF icon Appendix S Draft Trilogy Rehabilitation and Preliminary Closure Management Plan
PDF icon Appendix T Kundip Water Storage Facility NOI
PDF icon Appendix U Draft Kundip Rehabilitation and Preliminary Closure Management Plan
PDF icon Appendix V Modelling Effects of Tailings Emplacement
PDF icon Appendix W RAV 8 Site Water Balance
PDF icon Appendix X Impact of pit seepage
PDF icon Appendix Y Baseline Dust Monitoring - Kundip
2. Decision on whether to assess this proposal
Chair's Determination: 
Environmental Protection Statement (EPS)
Preliminary Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Thursday, 5 January, 2006
4. EPA Report on assessment
EPA Report Number: 
1213
EPA Report: 
PDF icon Phillips River Gold Project, Ravensthorpe
Date published: 
Thursday, 5 January, 2006
Appeals close: 
Thursday, 19 January, 2006
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Wednesday, 22 March, 2006
Ministerial Statement: 
PDF icon Ministerial Statement 716

Source URL:https://www.epa.wa.gov.au/proposals/phillips-river-gold-project