0682 - Goldsworthy Iron Ore Mines Expansion Project, 100 - 170 kms east of Port Hedland

Information

Attachment to Statement 682 – Change to description of proposal by removing Y4A from the main activity and increasing area disturbed from 97 to 145 hectares (ha) – change to proposal approved under section 45C on 8 June 2006.

Attachment 2 to Statement 682 – Revised proposal description and removal of Location, Duration and Employment from the key proposal characteristics; increase the area of disturbance from approximately 145 to 270 ha, and formalise new Maximum Disturbance Boundaries (Development Envelope) of approximately of 455 ha for the site – change to proposal approved under section 45C on 9 October 2013

Ministerial Statement File