Yarnima Power Station Stage 4 (Gas Reciprocating Engines)

Project
Proponent: 
BHP Iron Ore Pty Ltd
Proposal description: 

The proponent, BHP Iron Ore Pty, proposes to increase power generation capacity at the existing Yarnima Power Station, approximately 2 kilometres north-west of Newman in the Pilbara. The proposal comprises an increase in installed firm power generation capacity from 154 megawatts up to 239 megawatts via installation of gas reciprocating engines and associated infrastructure. The gas reciprocating engines are proposed to be installed in stages up to a maximum of 120 megawatts (nominal). 

Associated infrastructure included in the proposal includes switch rooms, electrical connections, a new gas heater, extension of fuel piping, water supply systems and other auxiliary equipment. 

Clearing of native vegetation is not proposed.

The Yarnima Power Station occurs within the Nyiyaparli Native Title Determination Area.

Peak annual greenhouse gas emissions are predicted to be: 

  • Scope 1 (power generation): 480,030 tonnes of CO2 equivalent per year (tCO2-e/yr) 

  • Scope 2: NA 

  • Scope 3 (fuel supply): 37,260 tCO2-e/yr. 

Assessment Number: 
2433
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Power generation
Last updated: 
November 29, 2024
Current Status: 
EPA Report and Recommendations released - appeals open
1. Referral
Comment on this referral: 
Yarnima Power Station Stage 4 (Gas Reciprocating Engines)
Comment period: 
Monday, 15 April, 2024 to Sunday, 21 April, 2024
Referral documentation: 
PDF icon Referral form
PDF icon Yarnima Power Station Stage 4 ERD.pdf
PDF icon Appendix 1 Yarnima Power Station Expansion PCD.pdf
PDF icon Appendix 5 Consolidated Vegetation Mapping (Onshore 2014).pdf
PDF icon Appendix 6 BHP Pilbara Regional GHGMP YPS Stg 4.pdf
PDF icon Appendix 7 GHGMP Peer Review (KPMG 2023).pdf
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Referral Information
Extract of determination: 
PDF icon Yarnima Power Station Stage 4 (Gas Reciprocating Engines)
Date published: 
Monday, 29 April, 2024
4. EPA Report on assessment
EPA Report Number: 
1776
EPA Report: 
PDF icon EPA Report 1776 Yarnima Power Station Stage 4.pdf
Key Environmental Factors: 
Greenhouse Gas Emissions
Date published: 
Thursday, 5 December, 2024
Appeals close: 
Friday, 27 December, 2024
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Friday, 17 January, 2025
Ministerial Statement: 
PDF icon Ministerial statement 1243.pdf