Project
Proponent: 
Cleanaway Solid Waste Pty Ltd
Proposal description: 

The Banksia Road Landfill is located in the Shire of Dardanup approximately 10 kilometres (km) from the City of Bunbury and 3.8 km south-east of the town of Dardanup. 

The Landfill is currently operating under a Licence issued through Part V of the Environmental Protection Act (Licence - L8904/2015/1) which allows for the acceptance of Liquid Waste; and Class II and Class III putrescible waste.  

The proposal would be a continuation of the current operations and including the establishment of additional landfill cells within the existing premises boundary.

Assessment Number: 
2303
Region: 
South West
Referred under EP Act: 
s38
Industry sector: 
Waste management
Last updated: 
November 21, 2023
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment on this referral: 
Banksia Road Landfill, Dardanup. Construction and Operation of Landfill Cells 9, 10 and 12A
Comment period: 
Monday, 12 July, 2021 to Sunday, 18 July, 2021
Referral documentation: 
PDF icon 02 - EPA referral cover letter - Cleanaway Banksia Road Cells 9, 10 and 12A .pdf
PDF icon Referral form
PDF icon Appendix E- B1026 Banksia Road Landfill Site Landscape and Visual Impact Assessment.pdf
PDF icon Appendix No. 01 - Cell 12A, 9 & 10 Development Site Plan.pdf
PDF icon Appendix No. 02 - Cell 12A Layout Plan.pdf
PDF icon Appendix No. 03 - Cell 9 Layout Plan.pdf
PDF icon Appendix No. 04 - Cell 10 Layout Plan.pdf
PDF icon Appendix No. 05 - Cell 12A Development Drawings.pdf
PDF icon Appendix No. 06 - Cell 9 Development Drawings.pdf
PDF icon Appendix No. 07 - Cell 10 Development Drawings.pdf
PDF icon Appendix No. 08 - Cell 12A Specification.pdf
PDF icon Appendix No. 09 - Cell 12A CQA Plan.pdf
PDF icon Appendix No. 10 - Environmental Management Plan V4.pdf
PDF icon Appendix No. 11 - Cell 12A Development Conceptual Top of Waste Surface Profile.pdf
PDF icon Appendix No. 12 - Cell 12A Development Conceptual Top of Waste Section.pdf
PDF icon Appendix No. 13 - Cell 9 Development Conceptual Top of Waste Surface Profile.pdf
PDF icon Appendix No. 14 - Cell 9 Development Conceptual Top of Waste Section.pdf
PDF icon Appendix No. 15 - Cell 10 Development Conceptual Top of Waste Surface Profile.pdf
PDF icon Appendix No. 16 - Cell 10 Development Conceptual Top of Waste Section.pdf
PDF icon Appendix No. 17 - WML Cell 12A Stability Assessment.pdf
PDF icon Appendix No. 18 - WML Cell 9 & 10 Internal Waste Stability Assessment.pdf
PDF icon Appendix No. 19 - Tonkin Leachate Balance Assessment Report.pdf
PDF icon Appendix No. 20 - Landfill Gas Management Plan.pdf
PDF icon Appendix No. 21 - Banksia Road Landfill Rehabilitation & Closure Plan V5.pdf
PDF icon Appendix No. 22 - Strategen Dust Management Plan.pdf
PDF icon Appendix No. 23 - Herring Storer Acoustics Environmental Acoustic Assessment.pdf
PDF icon Appendix No. 24 - Fire Control Process.pdf
PDF icon Attachment 2 3823AH_Rev3 Banksia Landfill GW Assessment.pdf
PDF icon Attachment 3 - 3823AK_Rev1_Banksia Road GW Assessment Letter Summary.pdf
PDF icon Attachment 4 - Banksia Road Letter Summary.pdf
PDF icon Attachment 5 - Dust Management Plan.pdf
PDF icon Attachment 6 - Environmental Management Plan V4.pdf
PDF icon Attachment 7 - CWY Dardanup Landfill Fire Control Process rev 2.pdf
PDF icon Attachment 8 - Works Approval Herring Storer Acoustics Environmental Acoustic Assessment.pdf
PDF icon Attachment 9 - Decision Report Response.pdf
PDF icon Dardanup Lease Renewal Fully Executed.pdf
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Additional Assessment Information (public review)
Extract of determination: 
PDF icon Cleanaway Banksia Road Landfill – New Storage Cells 9, 10 and 12A
Preliminary Environmental Factors: 
Social Surroundings
Inland Waters
Date published: 
Monday, 9 August, 2021
3. Assessment
Environmental Review
Public submissions: 
Monday, 13 March, 2023 to Sunday, 9 April, 2023
Make a submission: 
Banksia Road Landfill Dardanup Construction and Operation of Landfill Cells 9, 10 and 12A - Additional Information
Environmental Review documentation: 
PDF icon Banksia Rd Referral Document 220223.pdf
PDF icon Attachment A Works Approval Supporting Information.pdf
PDF icon Attachment B Groundwater MP.pdf
PDF icon Attachment C Stormwater MP.pdf
PDF icon Attachment D Visual Impact Assessment.pdf
PDF icon Attachment E Odour Impact Assessment.pdf
PDF icon Attachment F Asbestos Management.pdf
PDF icon Attachment G Groundwater Monitoring Well Report.pdf
PDF icon Attachment H Hydrogeological Risk Assessment.pdf
Date Published (Environmental Review documentation): 
March 13, 2023
Proponent response to submissions: 
PDF icon Banksia Road Landfill - Response to submissions.pdf
Date published (Proponent response to submissions): 
August 23, 2023
Minor or preliminary work under s. 41A(3)
s. 41A(3) notice: 
PDF icon 3.6 Notice - EPA decision on minor or preliminary work - Banksia Road Landfill.pdf
Date of approval s. 41A(3): 
Tuesday, 12 September, 2023
4. EPA Report on assessment
EPA Report Number: 
1747
EPA Report: 
PDF icon EPA Report 1747 - Banksia Road Landfill, Dardanup - assessment report.pdf
Key Environmental Factors: 
Social Surroundings
Date published: 
Thursday, 5 October, 2023
Appeals close: 
Thursday, 26 October, 2023
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 21 November, 2023
Ministerial Statement: 
PDF icon Ministerial Statement 1213