Pluto North West Shelf Interconnector Pipeline

Project
Proponent: 
DDG Operations Pty Ltd
Proposal description: 

The Proposal is to construct and operate the Pluto to Northwest Shelf Interconnector, a 3.3 km long, steel buried natural gas pipeline, connecting the Pluto Interconnector Compressor Station to the Karratha Gas Plant which is operated by Woodside on behalf of the North West Shelf Project participants, located on the Burrup Peninsula in the North of Western Australia.

The proposal will require the clearing of an estimated 10.69 ha.3.26 ha within the Karratha Gas Plant Lease and Buffer Zone Lease and 7.43 ha within Dampier to Bunbury Natural Gas Pipeline Corridor and Dampier facilities area.

Assessment Number: 
2192
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Oil and gas
Last updated: 
November 21, 2019
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment on this referral: 
Pluto North West Shelf Interconnector Pipeline
Comment period: 
Wednesday, 21 November, 2018 to Tuesday, 27 November, 2018
Referral documentation: 
PDF icon Referral Form and Suppoting Information
PDF icon Supporting Information - Appendices
PDF icon Additional Information - Construction Environmental Management Plan.pdf
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Additional Assessment Information
Extract of determination: 
PDF icon Pluto North West Shelf Interconnector Pipeline
Preliminary Environmental Factors: 
Social Surroundings
Flora and Vegetation
Terrestrial Fauna
Date published: 
Thursday, 24 January, 2019
4. EPA Report on assessment
EPA Report Number: 
1639
EPA Report: 
PDF icon EPA Report 1639 - Pluto North West Shelf Interconnector Pipeline
Date published: 
Tuesday, 4 June, 2019
Appeals close: 
Tuesday, 18 June, 2019
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Thursday, 21 November, 2019
Ministerial Statement: 
PDF icon Ministerial Statement 1117