South West Creek Dredging and Reclamation Proposal

Project
Proposal description

The proposal involves the dredging of not more than 14.2 million cubic metres (Mm3) of material for eight new berth pockets, a turning circle and a link to the existing shipping channel. The proposal also involves the construction of two new land based dredge management areas (DMMAs). Dredged material will be disposed offshore at an existing disposal ground in Commonwealth waters and the new and existing DMMAs.

Assessment Number
1856
Region
Referred under EP Act
s38
Industry sector
Last updated
Current Status
Ministerial Statement published
2. Decision on whether to assess this proposal
Date published
4. EPA Report on assessment
EPA Report Number
1380
Key Environmental Factors
Date published
Appeals close
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval
Post-assessment changes
S46C changes to conditions

Attachment 3 to Statement 859 – Change to conditions 6-1, 6-2, 6-3, 6-4, 6-5 & 6-6 – change to proposal approved under section 46C on 8 November 2013.

Date S46C
s. 45C amendments

Attachment 1 to Statement 859 – Relocation of DMMA G Discharge Point and Modification of Zone of Permanent Mangrove loss - change to proposal approved under s45C on 27 October 2011.

Attachment 2 to Statement 859 – Realignment of the access track between Utah Point Road and the dredging area, and associated changes to the zone of permanent mangrove loss – change to proposal approved under s45C on 2 May 2012.

Date of approval s. 45C