0490 - Industrial Infrastructure and Harbour Development, Jervoise Bay

Information

Attachment to Statement 490 - Construction of new infrastructure and deepening of harbour - change to proposal approved under s45C on 14 September 2006.

Attachment 1 to Statement 490 - Construction of wharf infrastructure and associated dredging - change to proposal approved under s45C on 16 March 2009.

Attachment 2 to Statement 490 - Changes:
• Construction of a 200 metre x 50 metre piled land backed wharf
• Up to 125 metre extension of the 350 metre long land backed wharf to 475 metres (AMC 1)
• Deck infill of AMC 2 by piling and cover with a concrete slab.
Changes to proposal approved under s45C on 24 May 2021.