Bunbury port, inner Harbour Extension

Project
Proponent: 
Bunbury Port Authority
Proposal description: 

Bunbury Port Authority proposes to extend the Inner Harbour at Bunbury by dredging a strip of land to the south-east of the existing basin, to allow for two additional ship berths and associated on shore facilities. The dredged spoil would be used to complete the filling of partially filled areas, to make them suitable in accordance with current zonings for bulk storage and port related activities.

Dredging would be undertaken by a cutter suction dredge to a depth of 12.2m. Material would be cut below sea bed level by the rotating cutter head, and drawn into a large diameter suction pipe to be pumped ashore. The dredged material would be mostly sand and silt. with smaller quantities of limestone and weathered basalt. If fresh basalt is found, controlled blasting would be required to remove it.

The total volume of dredged material is estimated at some 1.8 million m3. All the dredged spoil would be pumped hydraulically to reclamation areas. These are land areas to the north-east of the Inner Harbour, bounded by Vittoria Bay on the Leschenault Estuary, Preston River, existing alumina leases and State Electricity Commission land. They were partially filled when the current Inner Harbour was dredged in the early seventies.

Assessment Number: 
425
Region: 
South West
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Last updated: 
November 12, 1991
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Consultative Environmental Review
3. Assessment
Scoping
Approved: 
Friday, 8 June, 1990
Environmental Review
Public submissions: 
Tuesday, 27 November, 1990 to Friday, 21 December, 1990
Environmental Review documentation: 
PDF icon Consultative Environmental Review document
4. EPA Report on assessment
EPA Report Number: 
497
EPA Report: 
PDF icon Bunbury Port, Inner Harbour extension
Key Environmental Factors: 
Social Surroundings
Terrestrial Environmental Quality
Water
Inland Waters Environmental Quality
Date published: 
Friday, 8 March, 1991
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 12 November, 1991
Ministerial Statement: 
PDF icon Ministerial Statement 193

Source URL:https://www.epa.wa.gov.au/proposals/bunbury-port-inner-harbour-extension