Proposal description: 

The proposal involves the construction and operation of a hydro-electric power generation facility next to the main dam on the Ord River, using facilities established during initial dam construction for such a purpose.

When the dam wall was built, two tunnels were built to allow for provision and control of irrigation water, and the possibility of utilising waters from Lake Argyle to generate electricity.

The hydro-electric generating station would be built at the downstream "toe" of the dam. Two turbines would be installed with a combined generating capacity of 40MW at a lake level of 82m AHD or greater. While the majority of the structures would be below 'datum ground level', the superstructure, transformers and switching station would be above this level.

To de-water the site, a temporary coffer dam would be built some 100m downstream of the irrigation outlet, and would incorporate culverts to allow water through during this period.

Assessment Number: 
390
Region: 
Kimberley
Referred under EP Act: 
s38
Industry sector: 
Power generation
Last updated: 
April 29, 1992
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Date published: 
Thursday, 12 April, 1990
3. Assessment
Scoping
Approved: 
Friday, 1 June, 1990
Environmental Review
Public submissions: 
Saturday, 12 October, 1991 to Monday, 9 December, 1991
Environmental Review documentation: 
PDF icon PER document
4. EPA Report on assessment
EPA Report Number: 
615
EPA Report: 
PDF icon Ord River hydro-electric project
Date published: 
Saturday, 21 March, 1992
Appeals close: 
Friday, 3 April, 1992
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Wednesday, 29 April, 1992
Ministerial Statement: 
PDF icon Ministerial Statement 254