Yandicoogina (Marillana) iron ore project - change of environmental conditions due to increase in rate of production (s46) [875]

Project
Proponent: 
BHP Iron Ore limited
Proposal description: 

BHP Iron Ore has submitted a further proposal to increase the rate of production from 10 MTPA to 15 MTPA. This increase would require the following modifications to the present operation, approved under Ministerial Statement 29 as amended by Ministerial Statement 259:

  • minor modifications to the existing processing plant to increase its capacity to 11 MTPA;
  • the construction of additional processing facilities, as required, to increase capacity to 15MTPA;
  • a gradual increase in mobile mining equipment; and
  • a gradual increase in the workforce, requiring some additional facilities at the mine site village.

The remainder of the ore processing facilities, infrastructure and the final pit limits will not change. The increased mining rate will mean the ore body will notionally be mined out over 12 years rather than 16 years as previously envisaged at the 10 MTPA production rate.

Assessment Number: 
875
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Iron Ore
Last updated: 
June 1, 1994
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
s46 request for a change to environmental conditions (not subject to appeal): Public Notification
Date published: 
Friday, 11 March, 1994
4. EPA Report on assessment
EPA Report Number: 
738
EPA Report: 
PDF icon Yandicoogina Marillana iron ore project - change of environmental conditions due to increase in rate of production
Key Environmental Factors: 
Terrestrial Environmental Quality
Water
Hydrological Processes
Date published: 
Tuesday, 26 April, 1994
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Wednesday, 1 June, 1994
Ministerial Statement: 
PDF icon Ministerial Statement 357

Source URL:https://www.epa.wa.gov.au/proposals/yandicoogina-marillana-iron-ore-project-change-environmental-conditions-due-increase-rate