Home > Printer-friendly > Printer-friendly > Kemerton wastewater treatment plant and treated wastewater reuse at woodlot

Kemerton wastewater treatment plant and treated wastewater reuse at woodlot

Project
Proponent: 
Water Corporation
Proposal description: 

The proposal is for the works and operation of a wastewater treatment plant (WWTP) and woodlot reuse scheme for the first three years. This will enable monitoring and evaluation to be undertaken to determine a longer term strategy for development and operation of the scheme.

The proposed works and operation for the first three years form part of planned Stage 1 of the scheme, which will extend to the year 2010. A further two stages (extending to 2040) are planned for the future.

Assessment Number: 
1376
Region: 
South West
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Waste management
Last updated: 
October 1, 2019
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assessment on referral information (ARI)
Preliminary Environmental Factors: 
Flora and Vegetation
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Monday, 23 April, 2001
4. EPA Report on assessment
EPA Report Number: 
1011
EPA Report: 
PDF icon Kemerton Wastewater Treatment Plant and Treated Wastewater Reuse at Woodlot Binningup
Key Environmental Factors: 
Flora and Vegetation
Terrestrial Environmental Quality
Inland Waters Environmental Quality
Date published: 
Monday, 30 April, 2001
Appeals close: 
Monday, 14 May, 2001
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 26 June, 2001
Ministerial Statement: 
PDF icon Ministerial Statement 568.pdf
Post-assessment changes
Section 46 inquiry: 
Kemerton Wastewater Treatment Plant (s46) [2332]
s. 45C amendments: 

Attachment 1 to Statement 568 - Changes:

• Updated title and description to refer to Kemerton woodlot - Binningup woodlot deleted

• Refined general description of the wastewater treatment plant (WWTP) • Location description of the WWTP is updated to the current cadastral data description

• Removed references to the 2002, 2003 and 2004 projected treatment capacities - The current maximum treatment capacity (3.6 ML/day) is retained.

• Removed references to treated wastewater quality parameters (now retained solely under Part V Licence L7802)

• Removed reference to the 10 ML storage dam at Binningup and the 7.4 kilometre wastewater conveyance pipeline to Binningup, as neither will be constructed

• Removed reference to Eaton - as Eaton’s wastewater is now directed to Bunbury WWTP • Removed reference to 60 ha woodlot at Binningup

• Updated woodlot site details to reflect Kemerton woodlot - i.e general description, location, area (now 30ha)

• Removed 10ML on-site treated wastewater storage dam (no longer required at Binningup)

Changes to proposal approved under s45c on 1 October 2019

Date of approval s. 45C: 
Tuesday, 1 October, 2019