Derby Tidal Power Project [1453]

Project
Proponent: 
Tidal Energy Australia
Proposal description: 

The proposal is to construct and operate a tidal power station across the mouth of Doctor’s Creek, near Derby, for the generation of electricity.

The proposal also includes the construction of power lines to distribute power to major centres in the West Kimberley.

Note: This assessment is of a modification to the Derby Tidal Power proposal (previously reported in Bulletin 942 and Bulletin 984).

Assessment Number: 
1453
Region: 
Kimberley
Referred under EP Act: 
s38
Industry sector: 
Power generation
Last updated: 
July 22, 2013
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Referral documentation: 
PDF icon Notification of changes to the Derby Tidal Power Project
2. Decision on whether to assess this proposal
Chair's Determination: 
Formal under Section 43 (Not appealable)
Preliminary Environmental Factors: 
Flora and Vegetation
Landforms
Date published: 
Monday, 16 September, 2002
4. EPA Report on assessment
EPA Report Number: 
1071
EPA Report: 
PDF icon Derby Tidal Power Project
Key Environmental Factors: 
Benthic Communities and Habitats
Coastal Processes
Marine Environmental Quality
Date published: 
Monday, 7 October, 2002
Appeals close: 
Monday, 21 October, 2002
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Monday, 22 July, 2013
Ministerial Statement: 
PDF icon Ministerial Statement 941

Source URL:https://www.epa.wa.gov.au/proposals/derby-tidal-power-project-1453