Proposal description: 

The original proposal, as set out in the proponent’s PER, comprised four iron ore mines in the Pilbara region, an ore beneficiation plant, a borefield, an accommodation village and 160km of east-west railway connecting to the north-south link to Port Hedland.

Since release of the PER, FMG has made several major modifications to the proposal:

  • the proposed mines at Mt Lewin and Mt Nicholas have been excised;
  • the connecting infrastructure to those minesites is not now needed, leading to a change in the length of the railway from 160km to 111km (rail route option 3);
  • an alternative rail line crossing of the Chichester Ranges further to the east is proposed (option 3) versus the originally preferred option 2 route; and
  • overall disturbance has reduced from 17,107ha to 12,175ha, with a reduction in the amount of Mulga that will need to be cleared.
Assessment Number: 
1520
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Iron Ore
Last updated: 
March 28, 2012
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Preliminary Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Monday, 3 May, 2004
3. Assessment
Scoping
Environmental scoping document: 
PDF icon Scoping document (included as Appendix A to the PER)
Approved: 
Tuesday, 23 November, 2004
Environmental Review
Public submissions: 
Monday, 17 January, 2005 to Monday, 14 March, 2005
Environmental Review documentation: 
PDF icon PER document
PDF icon Appendix: Evaluation of Alternative Rail Routes
PDF icon Appendix: Surface hydrology
PDF icon Appendix: Water flow in Mulga areas adjoining Fortescue Marsh
PDF icon Appendix: Hydrology
PDF icon Appendix: Socio-economic assessment
PDF icon Appendix: Aboriginal heritage
PDF icon Appendix: Vegetation and flora survey
PDF icon Appendix: Potential Impacts on Groundwater Dependent Vegetation
PDF icon Appendix: Vegetation Disturbance
PDF icon Appendix: Fauna habitat and fauna assemblage survey
PDF icon Appendix: Subterranean fauna
PDF icon Appendix: Risk assessment
PDF icon Appendix: Christmas Creek deposit - Implications for Mine-Waste Management
PDF icon Appendix: Mindy Mindy deposit - Implications for Mine-Waste Management
PDF icon Appendix: Mt Lewin deposit - Implications for Mine-Waste Management
PDF icon Appendix: Mt Nicholas deposit - Implications for Mine-Waste Management
PDF icon Appendix: Noise impact assessment
PDF icon Appendix: Conceptual Mine Closure Plan
Proponent response to submissions: 
PDF icon Response to submissions
4. EPA Report on assessment
EPA Report Number: 
1202
EPA Report: 
PDF icon Pilbara Iron Ore Infrastructure Project: East-West Railway and Mine Sites Stage B
Key Environmental Factors: 
Flora and Vegetation
Subterranean Fauna
Terrestrial Environmental Quality
Date published: 
Monday, 31 October, 2005
Appeals close: 
Monday, 14 November, 2005
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Friday, 16 December, 2005
Ministerial Statement: 
PDF icon Ministerial Statement 707
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Statement 707 - Increase to Christmas Creek clearance area (by 12.5ha) - section 45C change to proposal approved on 21 October 2006.

Attachment 2 to Statement 707 - Alterations to rail corridor alignment and length - section 45C change to proposal approved on 3 October 2008.

Attachment 3 to Statement 707 - To haul iron ore from Christmas Creek to Cloud Break via truck along existing roads, in addition to the approved transportation by train - section 45C change to proposal approved on 23 June 2009.

Attachment 4 to Statement 707 - Additional impact area for rail duplication works (by 102ha) - section 45C change to proposal approved on 21 December 2009.

Attachment 5 to Statement 707 - to realign approximately 6 kilometres of the western portion of the access road used to haul ore from the Christmas Creek to Cloud Break mine sites - change to proposal approved under s45C on 15 March 2010.

Attachment 6 to Statement 707 - Extension of pipeline from the Hillside East reinjection borefield into the Christmas Creek mine site - change to proposal approved under s45C on 6 April 2010.

Attachment 7 to Statement 707 - Construction of additional rail infrastructure; Construction of an access/transport route between the Christmas Creek mine site and Marble Bar Road, as shown in Figure 8 (this replaces the section of road between the Christmas Creek mine site and Marble Bar Road depicted in Figure 3 of Attachment 1); and Removal of production rate from Key Characteristics Table - change to proposal approved under s45C on 28 March 2012.

Date of approval s. 45C: 
Saturday, 21 October, 2006
Friday, 3 October, 2008
Tuesday, 23 June, 2009
Monday, 21 December, 2009
Monday, 15 March, 2010
Tuesday, 6 April, 2010
Wednesday, 28 March, 2012

Source URL:https://www.epa.wa.gov.au/proposals/pilbara-iron-ore-and-infrastructure-project-east-west-railway-and-mine-sites-stage-b