South West Creek Dredging and Reclamation Proposal

Project
Proponent: 
Port Hedland Port Authority
Proposal description: 

The proposal involves the dredging of not more than 14.2 million cubic metres (Mm3) of material for eight new berth pockets, a turning circle and a link to the existing shipping channel. The proposal also involves the construction of two new land based dredge management areas (DMMAs). Dredged material will be disposed offshore at an existing disposal ground in Commonwealth waters and the new and existing DMMAs.

Assessment Number: 
1856
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Land use
Last updated: 
November 8, 2013
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment period: 
Thursday, 2 December, 2010 to Wednesday, 8 December, 2010
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Assessment on Proponent Information - Category A
Extract of determination: 
PDF icon 1856-ChairDets-201210.pdf
Preliminary Environmental Factors: 
Benthic Communities and Habitats
Marine Environmental Quality
Date published: 
Monday, 20 December, 2010
4. EPA Report on assessment
EPA Report Number: 
1380
EPA Report: 
PDF icon South West Creek Dredging and Reclamation Proposal
Key Environmental Factors: 
Benthic Communities and Habitats
Water
Date published: 
Monday, 10 January, 2011
Appeals close: 
Monday, 24 January, 2011
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 15 March, 2011
Ministerial Statement: 
PDF icon Ministerial Statement 859
Post-assessment changes
S46C changes to conditions: 

Attachment 3 to Statement 859 – Change to conditions 6-1, 6-2, 6-3, 6-4, 6-5 & 6-6 – change to proposal approved under section 46C on 8 November 2013.

Date S46C: 
Friday, 8 November, 2013
s. 45C amendments: 

Attachment 1 to Statement 859 – Relocation of DMMA G Discharge Point and Modification of Zone of Permanent Mangrove loss - change to proposal approved under s45C on 27 October 2011.

Attachment 2 to Statement 859 – Realignment of the access track between Utah Point Road and the dredging area, and associated changes to the zone of permanent mangrove loss – change to proposal approved under s45C on 2 May 2012.

Date of approval s. 45C: 
Thursday, 27 October, 2011