Port Hedland Solar Project

Project
Proponent: 
Alinta Energy Development Pty Ltd
Proposal description: 

Alinta Energy Development Pty Ltd proposes to develop a 90 Mega Watts (MW) AC solar facility situated on Unallocated Crown Land near Alinta Energy’s existing Port Hedland Power Station located within the Boodarie Strategic Industrial Area.  The proposal is located approximately 5 km south-west of South Hedland, adjacent to Great Northern Highway, within the Town of Port Hedland. 

The proposal consists of a 90 MW AC solar farm and a short (~2 km) transmission connection to the existing Port Hedland Power Station 66 kV switchyard. The Proposal will supply power to the 66 kV Port Hedland power system for which Alinta Energy is the network service provider. 

The proposal would include: 

  • 275 hectares (ha) disturbance footprint within the 342.8 ha Solar Development Envelope. 

  • 5 ha disturbance footprint within the 62.19 ha Transmission Access Corridor Development Envelope

Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Power generation
Last updated: 
June 7, 2022
Current Status: 
Decision on whether to assess has been published
Decision on whether to assess has been published
1. Referral
Comment on this referral: 
Port Hedland Solar Project
Comment period: 
Monday, 11 April, 2022 to Friday, 22 April, 2022
Referral documentation: 
PDF icon Referral Form
PDF icon Proposal Content Document
PDF icon Supporting Document
PDF icon IBSA packages to support S38 referral.pdf
PDF icon Appendix 1 - Baseline Flora and Vegetation Survey (Phoenix 2022).pdf
PDF icon Appendix 2 - Bushfire Managment Plan (BPP, 2022).pdf
PDF icon Appendix 3 - Detailed Terrestrial Fauna and Targeted Bilby Survey (Phoenix, 2022).pdf
PDF icon Appendix 4 - Bilby Management Plan (Preston Consulting, 2022).pdf
PDF icon Appendix 5 - Reflective Glare Assessment (SLR, 2022).pdf
PDF icon Appendix 6 - Dust Modelling Report (ETA, 2022).pdf
PDF icon Appendix 7 - Surface Water Assessment (RPS, 2022).pdf
2. Decision on whether to assess this proposal
Chair's Determination: 
Referral examined, preliminary investigations and inquiries conducted. Proposal not to be assessed under Part IV of the EP Act – Dealt with Under Part V Division 2 (Clearing) (Not appealable)
Extract of determination: 
PDF icon Port Hedland Solar Project
Date published: 
Tuesday, 7 June, 2022