Project
Proponent: 
Woodside Energy Ltd
Proposal description: 

Woodside Energy Ltd (Woodside) proposes to construct and operate the Woodside Solar Facility in the Maitland Strategic Industrial Area, located approximately 15 kilometres south-west of Karratha, in the Pilbara region of Western Australia. 

The proposal will generate electricity (up to 500 megawatts) from a large-scale solar photovoltaic (PV) farm and includes energy storage (battery) infrastructure.   

The Proposal is only for the infrastructure associated with the generation and storage of electricity from Solar PV. All transmission to deliver the power from the Solar Facility to customers would be delivered via the North West Interconnected System (NWIS), through existing, upgraded, or new infrastructure constructed, owned and operated by Horizon Power for all users of the NWIS. 

The proposal would include a total disturbance of 975.6  hectares (ha) within a development envelope of 1100.3 ha.

Proposal Content Document: 
PDF icon Woodside Solar Facility PCD (1).pdf
Assessment Number: 
2321
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Power generation
Last updated: 
February 29, 2024
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment on this referral: 
Woodside Solar Facility
Comment period: 
Monday, 10 January, 2022 to Sunday, 16 January, 2022
Referral documentation: 
PDF icon Attachment 1 - Woodside Solar Facility Referral of a proposal under s38 (Updated Template).pdf
PDF icon Attachment 2 - Woodside Solar Facility - Proposal Content Document.pdf
PDF icon Attachment 3 - Woodside Solar Facility - Referral Supporting Document.pdf
PDF icon Attachment 4 - Appendix A - Environmental Management Plan.pdf
PDF icon Attachment 5 - Appendix B - Cultural Heritage Management Plan.pdf
PDF icon Attachment 6 - 2019 Flora and Vegetation Survey.pdf
PDF icon Attachment 7 - Appendix D - Terrestrial Fauna Survey.pdf
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Additional Assessment Information (public review)
Extract of determination: 
PDF icon Woodside Solar Facility
Preliminary Environmental Factors: 
Social Surroundings
Flora and Vegetation
Terrestrial Fauna
Date published: 
Monday, 7 February, 2022
3. Assessment
Environmental Review
Public submissions: 
Monday, 27 February, 2023 to Friday, 17 March, 2023
Make a submission: 
Woodside Solar Facility - Additional Information
Environmental Review documentation: 
PDF icon Woodside Solar Facility Final ERSD.pdf
PDF icon Woodside Solar Facility Impact Reconcilliation Procedure_September 2022.pdf
PDF icon Appendix A. Woodside Solar Facility Environment Management Plan_ December 2022.pdf
PDF icon Appendix B. Woodside Solar Facility Social Surrounds (Cultural Heritage) Management Plan_September 2022.pdf
PDF icon Appendix C. Addendum to Flora and Vegetation Survey (V Long and Associates 2020) .pdf
PDF icon Appendix C. Flora and Vegetation Survey (V. Long and Associates 2019).pdf
PDF icon Appendix D. Fauna Survey Report (GHD 2022).pdf
PDF icon Appendix E. Woodside Solar Facility Weed Management Plan.pdf
Date Published (Environmental Review documentation): 
February 27, 2023
Proponent response to submissions: 
PDF icon Response to Submissions - Revision 2 .pdf
PDF icon Appendix A - Environment Management Plan .pdf
PDF icon Appendix B - Social Surroundings (Cultural Heritage) Management Plan .pdf
PDF icon Appendix E - Weed Management Plan.pdf
PDF icon Impact Reconciliation Procedure.pdf
PDF icon Woodside Solar Facility _ SRE Desktop Assessment _ Final.pdf
PDF icon Woodside Solar Facility Fauna Report - Final.pdf
Date published (Proponent response to submissions): 
July 26, 2023
4. EPA Report on assessment
EPA Report Number: 
1746
EPA Report: 
PDF icon EPA Report 1746 - Woodside Solar Facility s. 44 - Assessment report.pdf
Key Environmental Factors: 
Social Surroundings
Flora and Vegetation
Terrestrial Fauna
Date published: 
Wednesday, 13 September, 2023
Appeals close: 
Wednesday, 4 October, 2023
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Friday, 3 November, 2023
Ministerial Statement: 
PDF icon Statement 1212.pdf
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Ministerial Statement 1212 - An increase in the total development envelope by 0.96 ha (from 1,100.3 ha to 1,101.26 ha) for the construction of an access road connecting the Woodside Solar Facility to the North West Coastal Highway. The Proposal Content Document published in the Statement of Reasons for the section 45c supersedes the ‘Proposal Content Document attachment 2’ referred to in Ministerial Statement 1212. Changes approved under s. 45C on 29 February 2024.

Attachments: 
PDF icon Summary of Reasons.pdf
Date of approval s. 45C: 
Thursday, 29 February, 2024

Source URL:https://www.epa.wa.gov.au/proposals/woodside-solar-facility