EPA Western Australia
Published on EPA Western Australia (https://www.epa.wa.gov.au)

Home > Printer-friendly > Printer-friendly > Hamersley Agriculture Project

Hamersley Agriculture Project

Project
Proponent: 
Hamersley Iron Pty Ltd
Proposal description: 

The proposal involves establishing an agricultural scheme that comprises a series of irrigated pivot cells for hay production, and will aim to increase productivity and sustainability of pastoral operations in the Pilbara. The proposal will utilise mine water, surplus to other MMP2 requirements, and forms an important component of the integrated MMP2 water management strategy. The Project area is approximately 2,800 hectares of which a maximum of 1,815 hectares is to be disturbed. This includes 1,650 hectares of direct impact and 165 hectares of indirect impact.

Assessment Number: 
1878
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Last updated: 
August 24, 2016
Current Status: 
Ministerial Statement published
Ministerial Statement published
1. Referral
Comment period: 
Thursday, 17 February, 2011 to Wednesday, 23 February, 2011
Referral documentation: 
PDF icon Referral form
PDF icon Supporting documentation
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Assessment on Proponent Information - Category A
Extract of determination: 
PDF icon 1878-ChairDets-280311.pdf
Preliminary Environmental Factors: 
Flora and Vegetation
Date published: 
Monday, 28 March, 2011
4. EPA Report on assessment
EPA Report Number: 
1416
EPA Report: 
PDF icon Hamersley Agriculture Project
Key Environmental Factors: 
Social Surroundings
Flora and Vegetation
Water
Date published: 
Monday, 17 October, 2011
Appeals close: 
Monday, 31 October, 2011
5. Decision on proposal and implementation of proposal
Ministerial Statement
Comments: 

Implementation conditions 5 and 6 of Ministerial Statement 883 have been superseded by the Interim Implementation Conditions below, issued on 24 August 2016, which is to have effect until a further statement is published under section 45(5) as applied by section 46(8) of the Environmental Protection Act 1986. All other conditions of Statement 883 continue to have effect.

Date of approval: 
Monday, 5 December, 2011
Ministerial Statement: 
PDF icon Ministerial Statement 883
Post-assessment changes
Comments: 

Pursuant to section 46A(1) of the Environmental Protection Act 1986, a Notice of Interim Implementation Conditions was issued on 24 August 2016. The interim implementation conditions in this Notice are to have effect instead of implementation conditions 5 and 6 of Statement 883 dated 5 December 2011.

These Interim Implementation Conditions are to be read in conjunction with Statement 883 and are to have effect until a further statement is published under section 45(5) as applied by section 46(8) of the Environmental Protection Act 1986. All other conditions of Statement 883 continue to have effect.

Notice of Interim Implementation Conditions under Section 46A : 
PDF icon Ministerial Statement 883 - s46A Notice of Interim Implementation Conditions
Date of approval (46a): 
Wednesday, 24 August, 2016
s. 45C amendments: 

Attachment 1 to Statement 883 - Update description of the Hamersley Agriculture Project (HAP); restrict Schedule 1 to “Option A” that is being implemented; remove references to buffer zones and indirect impact areas; amendment to Development Envelope to include a buffer for the current access corridor connecting the Central and Eastern Agricultural areas; removal of elements that are not considered Key Proposal Characteristics or are managed under other legislation; amendment of Table 1 and addition of Tables 2, 3, 4 and 5; and amendment to Figure1, removal of Figure 2 - change to proposal under s45C approved on 18 August 2016.

Date of approval s. 45C: 
Thursday, 18 August, 2016

Source URL:https://www.epa.wa.gov.au/proposals/hamersley-agriculture-project