Home > Printer-friendly > Printer-friendly > Ammonium Nitrate Production Expansion Project: Phase 2, Kwinana

Ammonium Nitrate Production Expansion Project: Phase 2, Kwinana

Project
Proponent: 
CSBP Limited
Proposal description: 

The proposal is to expand CSBP's Kwinana Ammonium Nitrate Production Facility (ANPF) by incorporating additional components into the existing facility and re-engineering (debottlenecking) some existing components in order to increase ammonium nitrate production capacity from 520,000 tpa to 936,000 tpa.

Proposal Content Document: 
File Revised_Proposal_Content_Document.docx
Assessment Number: 
1834
Region: 
Perth
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Last updated: 
March 7, 2024
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Extract of determination: 
PDF icon 1834-Chairdets-100510.pdf
Preliminary Environmental Factors: 
Social Surroundings
Marine Environmental Quality
Terrestrial Environmental Quality
Date published: 
Monday, 10 May, 2010
3. Assessment
Scoping
Approved: 
Tuesday, 7 September, 2010
Environmental Review
Public submissions: 
Monday, 22 November, 2010 to Monday, 31 January, 2011
Environmental Review documentation: 
PDF icon PER document
PDF icon Appendix 1 Construction Environmental Management Plan
PDF icon Appendix 2 Greenhouse Gas Abatement Program
PDF icon Appendix 3 Environmental Noise Management Plan
PDF icon Appendix 4 Air Dispersion Modelling Report
PDF icon Appendix 5 Environmental Noise Assessment
PDF icon Appendix 6 Risk Assessment Technical Summary
Proponent response to submissions: 
PDF icon Response to Submissions - Kwinana Ammonium Nitrate
4. EPA Report on assessment
EPA Report Number: 
1407
EPA Report: 
PDF icon Ammonium Nitrate Production Expansion Project: Phase 2, Kwinana
Key Environmental Factors: 
Water
Hydrological Processes
Date published: 
Monday, 18 July, 2011
Appeals close: 
Monday, 1 August, 2011
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Thursday, 6 October, 2011
Ministerial Statement: 
PDF icon Ministerial Statement 875.pdf
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Statement 875 – Removal of "Greenhouse gas emissions" – change to proposal approved under section 45C on 3 January 2013.

Attachment 2 to Statement 875 – Increase the boundary of Project Area; addition of an ammonium nitrate emulsion plant and associated infrastructure; remove elements that are not a significant key characteristic relevant to the environment or are regulated under Part V of the Environmental Protection Act 1986; and update Figures and reference coordinates - change to proposal approved under section 45C on 24 January 2017.

Attachment 3 to Statement 875 – Removal of the authorised extent of up to 2.5 ML/day of liquid waste output from the Key Characteristics Table - change to proposal approved under section 45C on 13 August 2018.

Attachment 4 to Statement 875 – Debottlenecking at three existing nitric acid and ammonium nitrate (NAAN)
plants in order to increase production capacity of nitric acid and ammonium
nitrate solution.
• Installation of tertiary N2O abatement technology at NAAN plants 1 and 2 prior
to debottlenecking.
• Increasing ammonium nitrate emulsion production capacity.
• Increasing storage at the ammonium nitrate emulsion plant.
• Construction of additional nitric acid and ammonium nitrate solutions storage
and load-out infrastructure and acceptance infrastructure for third-party
ammonium nitrate solutions.
• Removal of storage capacity from the proposal elements.
• Increasing water inputs.
• Reduced NOx emissions.
• Clarification that power generation extent applies to each generators.

Change to proposal approved under section 45C on 7 March 2024.

Attachments: 
PDF icon S45C_Notice_and_Summary_of_Reasons (1).pdf
Date of approval s. 45C: 
Thursday, 3 January, 2013
Tuesday, 24 January, 2017
Monday, 13 August, 2018
Thursday, 7 March, 2024

Source URL:https://www.epa.wa.gov.au/proposals/ammonium-nitrate-production-expansion-project-phase-2-kwinana