Resource Recovery Facility, Red Hill

Project
Proponent: 
Eastern Metropolitan Regional Council
Proposal description: 

The proposal is to construct and operate a resource recovery facility within the existing Red Hill Waste Management Facility, City of Swan, for the processing of waste to produce energy, using either anaerobic digestion technology or gasification technology.

Assessment Number: 
1844
Region: 
Perth
Referred under EP Act: 
s38
Industry sector: 
Waste management
Last updated: 
November 14, 2023
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Extract of determination: 
PDF icon Chairman's Determination - Resource Recovery Facility, Red Hill
Preliminary Environmental Factors: 
Social Surroundings
Flora and Vegetation
Date published: 
Monday, 13 September, 2010
3. Assessment
Scoping
Environmental scoping document: 
PDF icon Environmental Scoping Document - Resource Recovery Facility, Red Hill
Approved: 
Monday, 24 October, 2011
Environmental Review
Environmental Review documentation: 
PDF icon Public Environmental Review - Resource Recovery Facility, Red Hill
Proponent response to submissions: 
Package icon Appendix 1 Response to submissions
4. EPA Report on assessment
EPA Report Number: 
1487
EPA Report: 
PDF icon Report 1487 - Resource Recovery Facility, Red Hill
Key Environmental Factors: 
Social Surroundings
Date published: 
Monday, 22 July, 2013
Appeals close: 
Monday, 5 August, 2013
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Wednesday, 9 July, 2014
Ministerial Statement: 
PDF icon Statement No. 976.pdf
Post-assessment changes
Section 46 inquiry: 
Resource Recovery Facility, Red Hill (S46) [2200]
s. 45C amendments: 

Attachment 1 and 2 to Statement 976 - Change to short description in Schedule 1 to allow aerobic composting. Removal of Schedule 2 for the gasification option. Proposal description is amended and condition 1, 6.1, 7.1 and 9 are amended. Change to conditions approved under s. 45C on 14 November 2023.

Attachments: 
PDF icon Resource Recovery Facility Red Hill s45C - Notice and Summary.pdf
Date of approval s. 45C: 
Tuesday, 14 November, 2023