Attachment 1 to Ministerial Statement 1017 - Changes:
• Increase in the Area of Disturbance by 151.5 ha from 1942 ha to 2093.5 ha
• Increase in the Development Envelope by 110.3 ha from 2514 ha to 2624.3 ha
• Decrease in native vegetation clearing by 2.9 ha from 156 ha to 153.1 ha
• Increase in the volume of overburden handled by 10 Mt from 164 Mt to 174 Mt
• Removal of Western Power corridor extension from Development Envelope
Change to conditions approved under S45c 14 May 2021.