Boddington Gold Mine Enhancement, Boddington

Project
Proponent: 
Worsley Alumina Pty Ltd
Proposal description: 

The proposal is to upgrade the existing Mine facilities by increasing the maximum daily process from 8 000 tonnes to 12 000 tonnes.

Ore would continue to be mined from the same orebody currently being mined. It is therefore expected that the proposed increases in the rate of production would shorten the overall project life from fifteen to possibly ten years.

The plant facilities required for the upgrading would be an additional crusher, a ball or semi-autogenous grinding mill, additional classification cyclones and a leach tank. Residue transfer pumps would also require upgrading. It is proposed that other areas of the plant would remain the same, and no additional clearing beyond the existing plant site perimeter would be required.

Assessment Number: 
156
Region: 
South West
Referred under EP Act: 
s38
Industry sector: 
Gold
Last updated: 
February 15, 1988
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Formal under Part IV
Date published: 
Sunday, 1 November, 1987
4. EPA Report on assessment
EPA Report Number: 
313
EPA Report: 
PDF icon Boddington Gold Mine Project - enhancement of facilities
Date published: 
Tuesday, 1 December, 1987
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Monday, 15 February, 1988
Ministerial Statement: 
PDF icon Ministerial Statement 19

Source URL:https://www.epa.wa.gov.au/proposals/boddington-gold-mine-enhancement-boddington