Home > Printer-friendly > Printer-friendly > Telfer Project, Power Supply and Infrastructure Corridor, Port Hedland to Telfer Gold Mine, Great Sandy Desert

Telfer Project, Power Supply and Infrastructure Corridor, Port Hedland to Telfer Gold Mine, Great Sandy Desert

Project
Proponent: 
Greatland Pty Ltd
Notice of Change of Proponent: 
PDF icon Notice of Change of Proponent - 161224.pdf
Proposal description: 

The proposal is to supply power to an expanded mining operation at the Telfer Gold Mine.

The proposed expansion of the Telfer Gold Mine associated with this proposal is being dealt with separately. That mine expansion is set out in a separate referral to the EPA (Newcrest Mining Limited 2002b).

The mine expansion and power supply proposals have been separated because it is likely that the mine and power supply will eventually be operated by different proponents. Nevertheless, the proposals have been developed and assessed in parallel.

The EPA's assessment of the mine expansion proposal is here.

Assessment Number: 
1444
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Gold
Last updated: 
May 2, 2012
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Environmental Protection Statement (EPS)
Preliminary Environmental Factors: 
People
Social Surroundings
Flora and Vegetation
Date published: 
Monday, 19 August, 2002
3. Assessment
Environmental Review
Environmental Review documentation: 
PDF icon Environmental Protection Statement - Telfer Extension Poer Supply and Infrastructure Corridor
PDF icon A1444_R1058_EPS_Figure 1.pdf
4. EPA Report on assessment
EPA Report Number: 
1058
EPA Report: 
PDF icon Telfer Project, Power Supply and Infrastructure Corridor, Port Hedland to Telfer Gold Mine, Great Sandy Desert
Key Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Date published: 
Monday, 19 August, 2002
Appeals close: 
Monday, 2 September, 2002
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 1 October, 2002
Ministerial Statement: 
PDF icon Ministerial Statement 605
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Ministerial Statement 605 - alteration to pipeline route from Port Hedland to Telfer - change to proposal approved under s45C on 19 August 2004.

Attachment 2 to Ministerial Statement 605 - Consolidation and Amendment of Key Characteristics Table, Option 1a. Supplying natural gas from Port Hedland via a buried pipeline to the Telfer Gold Mine for on-site electricity generation at a new open cycle gas fired power plant - change to proposal approved under s45C on 2 May 2012.

Date of approval s. 45C: 
Thursday, 19 August, 2004
Wednesday, 2 May, 2012

Source URL:https://www.epa.wa.gov.au/proposals/telfer-project-power-supply-and-infrastructure-corridor-port-hedland-telfer-gold-mine